Room(s) to Breathe

Riverside Elementary 

NJPA and Gordian helped to provide a solution to construction and timing problems faced by Riverside Elementary as they implemented an expansion to ease student crowding issues.

Due to a sudden influx of students, Riverside Elementary School in Brainerd, Minn., found itself in dire need of an expansion. It had reached the point during the 2014-15 school year that students were attending classes in an abandoned locker room.

Faced with the pressing deadline of an impending new school year, the district looked to National Joint Powers Alliance and Gordian ezIQC for a fast solution that still met procurement requirements.

At the onset of the project, the school laid out three stipulations:

  • Make the budget work;
  • Complete the project by the start of the school year; and
  • Use as many local subcontractors, suppliers and workers as possible.

Crews broke ground for the 12,150-foot addition in March 2015. The project scope included seven new classrooms, boys’ and girls’ bathrooms, plus bathrooms in two classrooms, a staff work space for copier machines and computers, and a staff bathroom. Overall, the project increased the school’s space by approximately 20 percent.

By accessing the competitively solicited ezIQC contract with Hy-Tec Construction, available through NJPA, the project was accelerated and the school district’s three main goals were achieved.

The project was completed within the budget, on time, and 93 percent of the subcontractors and suppliers were located within a 20-mile radius of the work site.

Earl Wolleat, Brainerd Public Schools director of building & grounds, praised the ezIQC process and work of Hy-Tec:

“It wasn’t on time, it was ahead of schedule. And that’s one of the things that still amazes me about this project. It came in on budget, and you know, that’s all somebody from buildings and grounds can expect is on time and on budget, [then] move on to the next project,” he says.

www.njpacoop.org

This article originally appeared in the issue of .

Featured

  • Oregon District Selects Builder for Multiple Renovation Projects

    The David Douglas School District in Portland, Ore., recently selected Balfour Beatty company Howard S. Wright to deliver $15.7 million in renovations and repairs across multiple schools and facilities, according to a news release. The district also partnered with BBL Architects for the projects’ designs.

  • Illinois District Breaks Ground on Two New Junior High Schools

    Joliet Public Schools District 86 in Joliet, Ill., recently began construction on two new junior high schools—the district’s first new schools since 2011, according to a news release. New facilities for Hufford Junior High School and Gompers Junior High School will serve the east and west sides of the city and be built next to their current facilities, which will be demolished after the project is complete.

  • California District Completes Second Phase of Construction on Innovation Campus

    The Milpitas Unified School District (MUSD) in Milpitas, Calif., recently announced that Phase Two of construction is complete on the MUSD Innovation Campus, according to a news release. The district is partnering with Blach Construction and Quattrocchi Kwok Architects (QKA) on the education and workforce development center, which will support Calaveras Hills High School.

  • TCU Completes Construction on New Medical School Building

    Texas Christian University in Fort Worth, Texas, recently completed construction on a new home for the Anne Burnett Marion School of Medicine, according to a news release. Arnold Hall, standing four stories and covering 95,000 square feet, is the university’s first major off-campus development.

Digital Edition