Chiller Plant Optimization Saves Money

chiller plant

Baylor saved more than $460,000 (about 24 percent of electricity costs), 5.8 million kilowatt-hours, and 8.6 million pounds of CO2 with Optimum Energy.

Baylor University in Waco, TX, had a typical chiller plant—it ran well, but it was a hodgepodge of equipment and it was managed manually. Operators judged once per shift when to add or shed electricity load based on demand. That imprecise, inconsistent process made the plant inefficient.

Kenneth Haltom, who manages Baylor’s energy services through a partnership with Aramark, and his team suspected that chiller plant optimization would be the best way to increase efficiency and reduce energy costs. There was good savings potential: the eight-chiller plant, which cools 4.9 million square feet of space 365 days a year, was using 32 million kWh of electricity annually.

The team brought in Optimum Energy to assess the opportunity, and found their hypothesis was right. Optimum installed its OptimumLOOP software and OptiCx platform. The closed-loop optimization solution reads data every 30 seconds and dynamically adjusts plant equipment in real time in response to changing conditions. The software determines the best operating conditions across the plant and makes on-the-fly changes to all eight chillers, water pumps and cooling tower equipment.

“OptimumLOOP made everything automatic, from slightly adjusting a single valve to improve water flow, to shedding entire machines from the system when demand decreases,” explains Haltom. “Each chiller operates at a different output and rate, depending on what gives us the greatest efficiency.”

In the first year of operation, plant efficiency went from 0.897 kW/ton to 0.681 kW/ton. Baylor saved more than $460,000 (about 24 percent of electricity costs), 5.8 million kilowatt-hours and 8.6 million pounds of CO2. Also, air-conditioned spaces became more comfortable, and chiller equipment is now easier to maintain.

“Chiller optimization offered us the biggest bang for the buck,” says Haltom. “The product from the chiller plant is better, more consistent, and it’s now based on real-time load rather than operator guesses.”

www.optimumenergyco.com

This article originally appeared in the College Planning & Management February 2018 issue of Spaces4Learning.

Featured

  • University of Wisconsin-Milwaukee Debuts New Chemistry Building

    The University of Wisconsin-Milwaukee in Milwaukee, Wis., recently celebrated the grand opening of a new Chemistry Building, according to a news release. The facility measures in at 163,400 square feet, stands four stories, and has the capacity for about 5,000 chemistry and biochemistry students.

  • North Dakota State University Starts Construction on Research Lab

    North Dakota State University in Fargo, N.D., recently began construction on the new, $78-million Bolley Agricultural Research Laboratory, according to a news release. The university partnered with JLG Architects and Clark & Enersen for the building’s design and with Kraus-Anderson for its construction.

  • Fellowes Announces Sponsorship of Healthy Green Schools & Colleges Program

    Fellowes, a worldwide provider of WorkLife needs product solutions, recently announced that it will be a Platinum sponsor of the Healthy Green Schools & Colleges program, according to a news release. The program from the Healthy Schools Campaign is intended to help facility professionals improve the educational experience for students and staff through sustainable facility operations and green schools.

  • Virginia Tech Establishes New Facility for School of Construction

    Virginia Tech recently partnered with construction management firm Procon Consulting to establish the Procon Innovation Center on its campus in Blacksburg, Va., according to a news release. The facility inside the university’s newly built Hitt Hall will offer hands-on collaboration and learning opportunities for students in the Myers-Lawson School of Construction and College of Engineering.

Digital Edition