Specialty Contractors Waterproof University Boathouse Practice Tank

Two Minneapolis contracting firms recently partnered to make some long-needed repairs to the University of Minnesota’s on-campus boathouse.

The university’s Irene Claudia Kroll Boathouse is located on the shore of the Mississippi River and is one of a very small number of on-campus boathouses in the U.S. The facility features an erg room, a locker room, coaches’ offices, boat storage, and a 7,500-gallon indoor practice tank on the second floor.

University of Minnesota boathouse

The structure was built in 2007, and over time, water that splashed or leaked out of the practice tank had begun seeping through the flooring into the first floor. The facility was originally built with a nonstructural topping slab and precast flooring planks.

Western Specialty Contractors – Minneapolis Branch and the Minnesota-based general contractor Gardner Builders teamed up for the repair process, which started in Nov. 2020 and finished this month. Gardner Builders removed the tank and installed a drainage system. Then, the Western Specialty Contractors crew repaired the concrete surrounding the new drains and other cracks in the topping slab.

Before the new tank was finally installed, Western applied a 125-mil Tremco PUMA waterproof coating system to the surrounding concrete floor as a last layer of protection. “The waterproofing is a very heavy-duty and durable system that comes with a 20-year warranty but will actually last much longer than that,” said David Grandbois, Assistant Branch Manager of WSC – Minneapolis. “To ensure that the floor was monolithic and free from variances, Western performed an electronic leak detection test on the floor, which found no discrepancies.”

Due to the pandemic, the facility has been closed, so there were no schedule conflicts between the construction team and the university rowing team.

About the Author

Matt Jones is senior editor of Spaces4Learning. He can be reached at [email protected].

Featured

  • North Carolina District Completes New Elementary School

    The Wake County Public School System (WCPSS) in Holly Springs, N.C., recently announced that construction on a new elementary school has finished, according to a news release. Rex Road Elementary School measures in at 133,000 square feet and is the fifteenth school that general contractor Balfour Beatty has completed for the district.

  • Texas District Finishes Construction on New Middle School, Admin Building

    The Westwood Independent School District recently held a ribbon-cutting ceremony for the new Westwood Middle School and Administration Building in Palestine, Texas, according to a news release. The campus covers 106,000 square feet and has the capacity for 650 students in grades 6–8, and it will also play home to the district’s staff and administration.

  • Elevating Campus Maintenance: How Power Wash Drones are Transforming Educational Facilities

    As today’s campuses grow larger and more architecturally complex, keeping exteriors clean, safe, and inviting has never been tougher. Facilities leaders are under constant pressure to stretch budgets, meet safety standards, and support sustainability goals—all while tackling the stubborn challenge of exterior cleaning.

  • Anderson Brulé Architects Rebrands as ABA Studios

    Anderson Brulé Architects, based in San Jose, Calif., recently announced that it is celebrating 40 years of service by rebranding under a new name, according to a news release. The architectural, interior design, and planning firm will now be known as ABA Studios to refresh its identity underneath a new generation of leadership.

Digital Edition