Specialty Contractors Waterproof University Boathouse Practice Tank

Two Minneapolis contracting firms recently partnered to make some long-needed repairs to the University of Minnesota’s on-campus boathouse.

The university’s Irene Claudia Kroll Boathouse is located on the shore of the Mississippi River and is one of a very small number of on-campus boathouses in the U.S. The facility features an erg room, a locker room, coaches’ offices, boat storage, and a 7,500-gallon indoor practice tank on the second floor.

University of Minnesota boathouse

The structure was built in 2007, and over time, water that splashed or leaked out of the practice tank had begun seeping through the flooring into the first floor. The facility was originally built with a nonstructural topping slab and precast flooring planks.

Western Specialty Contractors – Minneapolis Branch and the Minnesota-based general contractor Gardner Builders teamed up for the repair process, which started in Nov. 2020 and finished this month. Gardner Builders removed the tank and installed a drainage system. Then, the Western Specialty Contractors crew repaired the concrete surrounding the new drains and other cracks in the topping slab.

Before the new tank was finally installed, Western applied a 125-mil Tremco PUMA waterproof coating system to the surrounding concrete floor as a last layer of protection. “The waterproofing is a very heavy-duty and durable system that comes with a 20-year warranty but will actually last much longer than that,” said David Grandbois, Assistant Branch Manager of WSC – Minneapolis. “To ensure that the floor was monolithic and free from variances, Western performed an electronic leak detection test on the floor, which found no discrepancies.”

Due to the pandemic, the facility has been closed, so there were no schedule conflicts between the construction team and the university rowing team.

About the Author

Matt Jones is senior editor of Spaces4Learning. He can be reached at [email protected].

Featured

  • UT System Approves First Funds for New Campus

    The University of Texas System Board of Regents recently approved funds to build the first facility of a new campus in far west Fort Worth, Texas, according to university news. UTA West will serve as a branch of the University of Texas at Arlington and is scheduled to open in fall 2028.

  • El Paso District Breaks Ground on New Elementary School

    The Canutillo Independent School District in El Paso, Texas, recently announced that construction has begun on a 119,000-square-foot elementary school, according to a news release. The district partnered with Pfluger Architects, Carl Daniel Architects, and LDCM Solutions on the new Davenport Elementary School, which has an expected completion date of 2027.

  • South Carolina District Starts Construction on $50M Middle School Renovation

    The Aiken County Public School District in North Augusta, S.C., recently held a groundbreaking ceremony for the $50-million renovation and expansion of North Augusta Middle School, according to a news release. The project’s funding comes from the 2024 renewal of a one-cent sales tax approved by local voters.

  • T&T Construction Management Group Completes Pasco High School Expansion

    Pasco High School in Dade City, Fla., recently announced that it has completed an expansion project in partnership with T&T Construction Management Group, Inc., Harvard Jolly Architecture, and Williams Company.