Buena Vista Middle/High School

TreanorHL

Project of Distinction Award 2021 Education Design Showcase

Buena Vista Middle/High School exterior

Project Information

Facility Use: Middle School / High School
Project Type: Renovation / Addition
Category: Whole Building / Campus Design
Location: Buena Vista, CO
District/Inst.: Buena Vista School District
Chief Administrator: Lisa Yates, Superintendent
Completion Date: December 2020
Gross Area: 134,000 SF
Area Per Student: 149 SF
Site Size: 31 acres
Current Enrollment: 507 students
Capacity: 937 students
Cost per Student: $44,823
Cost per Sq. Ft.: $313.43
Total Cost: $42,000,000

Buena Vista Middle/High School multi-purpose room

Nestled in the Arkansas River Valley, at an elevation of 7,965 feet above sea level, Buena Vista, Colorado—Spanish for "Good View"—is surrounded by 14,000-foot peaks, open skies, rivers, and agricultural lands.  With these remarkable environmental attributes in mind, the design for replacing the existing middle school/high school incorporates daylight, views, and connection to the outdoors at every location. The new, 120,000-square-foot school was designed to allow construction to occur in multiple phases, allowing the school to remain fully occupied throughout construction. The project was partially funded through the State of Colorado's Building Excellent Schools Today (BEST Program). The new building achieved a LEED Silver Certification.

Buena Vista Middle/High School staircase

The community played an essential role in the school’s design. An Architectural Recommendation Committee (ARC) was formed to provide transparent communication between the school district, the Buena Vista community, and the design team.  It was clear from the onset of the design work that the community was at the forefront of the school's design and design process. We began working with the Buena Vista School District with the active community as key contributors.

Buena Vista Middle/High School library

We initiated the process with an Architectural Recommendation Committee (ARC) comprising of 34 individuals: 19 from the school (staff and students) and 15 community residents (parents and key town stakeholders). This balance was a clear indicator of the ARC's goal to create a community school that was a centerpiece of the town of Buena Vista. The ARC was vital in the design process, providing a transparent dialogue between the school district, the Buena Vista community, and the design team. The ARC's design work sessions were instrumental in developing a school environment that supports the high-performing, programmatic goals of the Buena Vista School District while enriching the connections and partnerships with the community. The specific objectives of the ARC were established, and the project achieved the following goals:

  • Student-Centered
  • Student Well-Being
  • Create Opportunities for Exchange and Connection
  • Preparation of Students to Go Anywhere and Do Anything
  • Enhance the Family Culture
  • Outdoor Connections to the Environment

Buena Vista Middle/High School gym

The primary instructional classroom building is configured on two floors to separate middle- and high-school students. Each floor includes science classrooms/labs and small group rooms located between traditional classrooms. The shared programs—such as band, art, family and consumer studies, and industrial arts—are centrally located for easy access. The Information Commons is located on both floors and features flexible seating, movable shelving, and robust technology. A new student and visitor entry is located between the existing main gymnasium and the new auxiliary gymnasium.

Buena Vista Middle/High School hallway

With limited funds and the inability to afford a performing arts theater, a multi-functional space designated as the Flex Commons was created. The Flex Commons is located near the heart of the school and is connected by a main street that runs the length of the new school. This flexible space is used as a café and dining area, classroom, and theater. This space provides easy access to an outdoor eating area and learning space with views of the Collegiate Peaks. The Flex Commons is also used for larger staff presentations, meetings, and community events.

Connection to the outdoors was a major goal of the design committee. Tall windows allow for amazing daylighting and views; a likeness of the Arkansas River runs through the main floor; and stone, wood, and earth tones reflect Buena Vista's natural surroundings. The courtyards around the building were developed for outdoor learning opportunities, public gathering areas, and easy access to public trails adjacent to the site.

Buena Vista Middle/High School band room

Buena Vista Middle-High School achieved LEED Silver Certification and was designed to optimize natural daylight into all academic and activity zones of the school. Solar shading devices and high-performance glazing strategies achieved the sustainability goals to allow for solar and view access to and from 95% of the educational environment, including athletic areas.

A safe school site design was a vital goal of the community, and developing a "Front Yard" provides clear visibility of parking and drop zones while allowing for outdoor classroom areas and community courtyards. Indoor air controls and learning environment acoustic performance of STC 50 and higher were achieved, and low-flow plumbing fixtures were integrated within all new and renovated areas of the school.

Buena Vista Middle/High School exterior

Architect:

TreanorHL
STEPHANIE GROSE, AIA
303-298-4700

Featured

  • Florida Elementary School to Undergo $47M Reconstruction

    The School District of Osceola County in Kissimmee, Fla., recently announced a partnership with construction firm Skanska to reconstruct Reedy Creek Elementary School, according to a news release. The $47-million project will involve the new construction of a 96,000-square-foot academic center, renovating the remaining facilities, a full-site redevelopment, and demolishing portions of the existing school.

  • Fort Collins to Convert 1980s Office Park into Junior High School

    The Liberty Common School, a charter-public school in Fort Collins, Colo., recently broke ground on an adaptive reuse project that will convert an 1980s-era office park into a 45,000-square-foot junior high school for seventh- and eighth-grade students, according to a news release.

  • New Jersey PreK–12 School Breaks Ground on New STEM Building

    Saddle River Day School (SRDS) in Saddle River, N.J., recently announced that it has broken ground on the new Dr. Kristen Walsh Hall of Science & Entrepreneurship, according to a news release. The school partnered with DIGroup Architecture for the design of the new facility, which will provide the school with space to expand its STEM and business education classes.

  • American University Launches Sustainability Research Project

    American University in Washington, D.C., recently began a research project exploring the relationship between purchase decisions for university campuses and sustainability, according to a news release. The study seeks to explore how “greening” the purchases involved in student housing renovations, breaking ground on new facilities, buying new equipment and supplies, and more, can foster larger sustainability goals.