Construction of Interim Science Building Completed at Saint Louis University

St. Louis Science BuildingMcCarthy Building Companies, Inc. has completed the conversion of a former charter elementary school into an interim science building for Saint Louis University (SLU). The 50,000-sq.-ft. renovation, which was undertaken and opened in time for fall 2017 semester, now houses research, teaching and office space for the University’s Department of Biology. Located on SLU’s South Campus, the new facilities will serve students, researchers and faculty while the University renovates Macelwane Hall, which experienced a fire and subsequent water damage in May 2017.

McCarthy completed the fast-track construction project in seven weeks to ensure the building would be ready for the start of classes on August 28.

“We quickly mobilized our team and collaborated closely with SLU’s staff and Fox Architects to convert the vacant school into a state-of-the-art science learning environment,” says Ryan Freeman, vice president at McCarthy Building Companies. “The project involved a lot of hands-on ingenuity and innovation to meet the very quick timeframe.”

To avoid project delays and reduce costs, the construction team proactively surveyed and sourced laboratory casework and equipment salvaged from the fire, then reworked it to fit the programs and layout in the new spaces. 

Located at the corner of Spring and Chouteau Avenues, the former Imagine charter elementary school building required installation of lab exhaust and other systems and equipment, as well as extensive rework of mechanical and electrical systems to accommodate advanced research and teaching labs. 

“We relied on McCarthy’s efficiency and specialized expertise in building complex research and education spaces to complete the project on time,” says Dustin Montgomery, assistant director of construction services of Saint Louis University.

Featured

  • Northeastern University Breaks Ground on New Housing Community

    Northeastern University recently announced the groundbreaking of a new student housing community on its campus in Boston, Mass., according to a news release. The university is partnering with American Campus Communities (ACC) for development of the project, which will have the capacity for 1,200 students and has a scheduled completion date of fall 2028.

  • Beyond Four Walls

    Operable glass walls provide a dynamic solution for educational spaces. They align with today’s evolving teaching methods and adapt to the needs of modern learners. Beyond the functional versatility, movable glass walls offer clean, contemporary aesthetics, slim and unobtrusive profiles, and versatile configurations that cater to the evolving needs of students and educators alike.

  • California K–12 District Completes Elementary School Campus Replacement

    The West Contra Costa Unified School District (WCCUSD) in Richmond, Calif., recently announced the completion of a replacement campus for Lake Elementary School, according to a news release. The school has capacity for 470 students between Transitional Kindergarten (TK) and sixth grade.

  • UNT Dallas Holds Ribbon-Cutting Ceremony for $100M STEM Building

    The University of North Texas at Dallas in Dallas, Texas, recently celebrated the opening of its new, $100-million STEM Building, according to local news. The ceremony on Dec. 2 preceded the first day of classes in the facility on Jan. 12, 2026.