Managing Delays From the Construction Side

Not all construction delays are the fault of the construction contractor. By keeping the lines of communications open, the client and contractor together can work to avoid any serious slowdowns in the project.

Project managers should be aware of early warning of delays caused by the client, main contractor or your own people. Client delays arise because they may change their minds, give instructions too late or are slow in approving drawings and plans. They tend to overlook the fact that these delays push back the start for contractors or sub-contractors, and that the contractor is powerless to avoid these delays.

Main contractor delays usually involve construction work being completed late, causing subsequent stages to fall behind schedule. In some cases, delays are the result of mismanagement and a lack of coordination.

Last but not least, the subcontractors themselves may cause delays; for example, by under-resourcing the project in the early stages or by not completing design drawings and getting them approved on time.

Make sure delays outside your control are recognized and documented. Such delays can impact you financially and need to be recorded and the financial impact dealt with by the responsible party. You should not have to bear the cost of other peoples’ delays, nor should you be blamed for them.

This article originally appeared in the issue of .

Featured

  • DFW-Area District Opens New Replacement Middle School

    The Eagle Mountain-Saginaw Independent School District near Fort Worth, Texas, recently held a ribbon-cutting ceremony for a new replacement middle school campus, according to a news release. The new facility for Wayside Middle School, originally established in 1964, was built on the site of the former district administration building and funded through Bond Proposition A in 2023.

  • LAN, Inc. Opens Office in College Station, Texas

    Lockwood, Andrews & Newnam, Inc. (LAN) recently announced the opening of a new office in College Station, Texas, to support its regional client base, according to a news release. The organization provides engineering, design, and program management services for water, wastewater, transportation, stormwater, and education clients in the Brazos Valley.

  • UT System Approves First Funds for New Campus

    The University of Texas System Board of Regents recently approved funds to build the first facility of a new campus in far west Fort Worth, Texas, according to university news. UTA West will serve as a branch of the University of Texas at Arlington and is scheduled to open in fall 2028.

  • iPark 87

    Building a Future-Focused Career and Technical Education Center

    A district superintendent shares his team's journey to aligning student passions with workforce demands, and why their new CTE center could be a model for districts nationwide.