Managing Delays From the Construction Side

Not all construction delays are the fault of the construction contractor. By keeping the lines of communications open, the client and contractor together can work to avoid any serious slowdowns in the project.

Project managers should be aware of early warning of delays caused by the client, main contractor or your own people. Client delays arise because they may change their minds, give instructions too late or are slow in approving drawings and plans. They tend to overlook the fact that these delays push back the start for contractors or sub-contractors, and that the contractor is powerless to avoid these delays.

Main contractor delays usually involve construction work being completed late, causing subsequent stages to fall behind schedule. In some cases, delays are the result of mismanagement and a lack of coordination.

Last but not least, the subcontractors themselves may cause delays; for example, by under-resourcing the project in the early stages or by not completing design drawings and getting them approved on time.

Make sure delays outside your control are recognized and documented. Such delays can impact you financially and need to be recorded and the financial impact dealt with by the responsible party. You should not have to bear the cost of other peoples’ delays, nor should you be blamed for them.

This article originally appeared in the issue of .

Featured

  • Understanding the Training of School Resource Officers

    SROs are now integral components of nearly every educational system in the country. But instead of being a more passive entity in schools, they have gradually become mentors to students, adding to their support network of teachers, parents, coaches, and other caring adults.

  • University of Florida to Start Construction on New Agricultural, Engineering Building

    The University of Florida in Gainesville, Fla., recently announced that it will soon begin construction on a new academic building for the department of agricultural and biological engineering (ABE), according to a news release. The W.W. Glenn Teaching Building is scheduled to begin construction by the end of 2024 and finish by August 2025, in time for the new academic year.

  • University of Kentucky Receives $2.5M Donation Toward Renovation Project

    The University of Kentucky in Lexington, Ky., recently announced that it has accepted a $2.5-million donation that will transform Pence Hall into the home of the university’s College of Communication and Information, according to a news release.

  • San Diego High School Hits Construction Milestone

    Part of a whole-site modernization project at Mira Mesa High School in San Diego, Calif., recently reached a construction milestone. The final steel beam of the new classroom and student services facility was put into place, completing the building’s structural framework.

Digital Edition