Four Portland Schools Get Major Upgrades

As classes begin Aug. 28, Portland Public Schools continues construction and renovations on several schools that will be completed in the coming years.

In 2017, voters approved a nearly $800 million bond measure to improve and rebuild four schools. Here’s a brief overview of the district’s construction plans:

Kellogg Middle School

Kellog Middle School's rebuild will include learning suites that promote greater student collaboration.

The original school has been closed for over a decade and was demolished in 2018 to make way for a new building. The $60 million project is headed by OH Planning + Design, Architecture and is set to open in 2021.

Features include:

  • A cafeteria/commons area which serves as the heart of the school;
  • Learning suites that promote greater collaboration;
  • A performing arts stage that opens up to the gym, offering a flexible space for performances, assemblies and other community events;
  • An outdoor, multi-use field and walking path;
  • A STEAM lab and learning garden; and
  • Digital learning tools found throughout the campus for studies in energy use and sustainability.

Madison High School

Madison High School will feature a state-of-the-art performing arts facility.

While the school is under construction, students will attend Marshall High School. The rebuild will add about 170, 000 square feet and will open in 2021. Opsis Architecture, in collaboration with DAO Architecture, hope to transform the school into a “true 21st century learning environment and vibrant center for its thriving, diverse, multicultural, and multi-ethnic community.”

Plans for the school include:

  • A cafeteria/commons area;
  • Science labs;
  • A state-of-the-art performing arts facility;
  • A child care center, public health clinic and community food pantry to serve as resources for the community;
  • A new gym that seats 1,700; and
  • Specialty Career Technical Education labs and a new maker space.

Lincoln High School

Lincoln High School's new building is set to open in 2022 and the new athletic field facilities will be completed by 2023. Bora Architects are spearheading the project.

Construction for the school is planned in two phases and will begin next summer. The school building is set to open in 2022 and the new athletic field facilities will be completed by 2023. Bora Architects are spearheading the project.

Lincoln HS highlights include:

  • A cafeteria, commons and plaza;
  • Specialized classrooms for fine arts and flexible spaces for display of student work;
  • STEM labs and a maker space;
  • A new 1,700 seat gym and new track and field;
  • A 500-seat auditorium, a black box theater and band and choir classrooms; and
  • Specialized classrooms for Career Technical Education courses.

Benson Polytechnic High School

Construction on Benson will start in 2021 after Madison High School is completed. Students and staff would have to be relocated to Marshall High School while construction is underway. Bassetti Architects will spearhead the proposed modernization of Benson. The project is aimed to be completed by 2024.

About the Author

Yvonne Marquez is senior editor of Spaces4Learning. She can be reached at [email protected].

Featured

  • Anderson Brulé Architects Rebrands as ABA Studios

    Anderson Brulé Architects, based in San Jose, Calif., recently announced that it is celebrating 40 years of service by rebranding under a new name, according to a news release. The architectural, interior design, and planning firm will now be known as ABA Studios to refresh its identity underneath a new generation of leadership.

  • California Middle School Completes Two New Academic Buildings

    Sunnyvale Middle School in Sunnyvale, Calif., recently announced that construction is complete on two new classroom buildings of two stories each, according to a district news release. The new wing will house seventh- and eighth-grade students and is part of a larger campus modernization project.

  • KI Launches K–12 Classroom Furniture Giveaway

    Contract furniture company KI recently announced the launch of its fourth-annual Classroom Furniture Giveaway, which awards $50,000 each to four K–12 educators across the U.S., according to a news release. The goal is to address decreasing student engagement and increasing teacher burnout numbers by updating learning spaces to accommodate modern needs.

  • Malibu High School Campus Completes $102M Phase 1 of Construction

    Malibu High School in Malibu, Calif., recently announced that it has completed phase 1 of construction for its new campus, a news release reports. The first phase consisted of developing and modernizing the site of a former elementary school into a new, 70,000-square-foot, two-story facility.

Digital Edition