High-School Construction to Finish Early, Under Budget Due to COVID

Construction work on Hendersonville High School, located in Hendersonville, N.C., is set for completion in August 2022—11 months ahead of schedule. The project will also come in about half a million dollars under its $59.1-million budget.

Henderson County Capital Projects Manager David Berry attributes the accelerated timeline to sitework during the summer before construction, as well as a reduced student presence in the school due to the COVID-19 pandemic that allowed workers more and longer access to the site. He announced the news to the Board of Commissioners, who voted to amend its contract with Vannoy Construction to incorporate the new schedule and financial information.

“This is, for me, exciting news to bring forward to this board,” said Berry. “This whole project has been not only the most expensive that Henderson County—I believe—has taken on; it’s been the most difficult. And without everybody’s cooperation, we wouldn’t be where we are.”

The project includes renovations to two campus buildings (the Stillwell Building and the gymnasium completed in 1974) as well as a new-two story building. The new building will play home to administrative offices; a student media center; a new cafeteria; and new science, chorus, and band classrooms. The new building is set to open in August 2021 instead of its original December 2021 completion date.

“Students are going to benefit from this,” said Henderson County Public Schools Superintendent John Bryant. “Taxpayers are going to benefit from this. While logistical challenges will be presented, we welcome those challenges. We know that we’ll be successful in meeting those challenges because they benefit the children of our community.”

About the Author

Matt Jones is senior editor of Spaces4Learning. He can be reached at [email protected].

Featured

  • Texas State University Completes Stadium Renovations

    Texas State University in San Marcos, Texas, recently announced that it has completed a series of additions and renovations to its football stadium, according to a news release. Formerly known as the Bobcat Stadium End Zone Complex, the Johnny and Nathali Weisman Football Performance Center is an 85,000-square-foot expansion featuring hospitality spaces, banquet spaces, exterior concourses, and upgrades to the field house.

  • Upcoming University of Alabama Performing Arts Center Hits Construction Milestone

    The University of Alabama in Tuscaloosa, Ala., recently celebrated the topping out of its new Smith Family Center for Performing Arts, according to a news release. The university is partnering with HPM for program and project management on the facility, which broke ground in 2023 and is scheduled for completion in November 2026.

  • University of Utah Launches Utah 360 App

    The University of Utah in Salt Lake City, Utah, recently announced that it has partnered with digital engagement hub Pathify to launch a new app for the university community, according to a news release.

  • South Texas K–12 District Debuts Region’s First Electric Bus Fleet

    The Valley View Independent School District in Pharr, Texas, recently announced a partnership with Highland Electric Fleets to launch the district’s—and the region’s—first fleet of all-electric school buses, according to a news release.

Digital Edition