Construction Delays Opening of Ky. Middle School

When school starts on Thursday, Aug. 12, students of East Hardin Middle School in Hardin County, Ky., will return to their old building instead of a brand-new facility as originally expected. Officials say construction problems and electrical issues have resulted in the postponement of the new building’s grand opening. Students were originally supposed to make the move in January before COVID-related complications pushed the date to August. Now, the opening has been delayed again.

“We’ve ran into some electrical issues and just haven’t been able to get where we wanted to be,” said John Wright, Hardin County Schools spokesperson.

Alliance Corp. CEO Tommy Gumm cites a current “inability” to complete the work, failing to meet promised deadlines, and delays in finishing aspects like fire alarm systems on the part of the electric company. Likewise, Hardin County Schools (HCS) Chief Operations Officer John Stith said that the deadline of completing the fire alarm system was missed, which pushed the work to a minimum of a week behind schedule. He also cited delays that came earlier in the process, like masonry work.

On Aug. 1, the HCS Board of Education approved a temporary virtual learning option for East Hardin Students. Later that week, the district announced that in-person instruction would be available at the school’s old location.

“The thoughts of those involved with the construction today [Tuesday, Aug. 3] confirmed our fears about a timely certification of occupancy,” said HCS Superintendent Teresa Morgan. “What we heard today means that virtual instruction would’ve taken place for possibly longer than a month. We had hoped the virtual instruction would not last longer than seven days, and we’d be able to transition into the new building. Any construction project, especially one as large as a new school building, always brings variables and uncertainties.”

Officials have not yet provided an updated timeline on when the $24-million building will be ready for students. “It’s just really uncertain right now,” said Wright. Morgan agreed that the district will communicate with families regarding the building’s opening.

About the Author

Matt Jones is senior editor of Spaces4Learning. He can be reached at [email protected].

Featured

  • DLR Group Appoints New K–12 Education Practice Leader

    Integrated design firm DLR Group recently announced that it has named its new global K–12 Education leader, Senior Principal Carmen Wyckoff, AIA, LEED AP, according to a news release. Her teams have members in all 36 of the firm’s offices in the U.S., Puerto Rico, the U.S. Virgin Islands, Europe, and Asia.

  • Abstract tech network data connections with orange, blue glowing dots, lines

    3 Trends for Higher Education to Stay Ahead of in 2026

    As universities enter the new year, the question is no longer whether digital transformation is necessary, but how quickly institutions can convert technological potential into strategic advantage.

  • Beyond Four Walls

    Operable glass walls provide a dynamic solution for educational spaces. They align with today’s evolving teaching methods and adapt to the needs of modern learners. Beyond the functional versatility, movable glass walls offer clean, contemporary aesthetics, slim and unobtrusive profiles, and versatile configurations that cater to the evolving needs of students and educators alike.

  • Little Grand Market

    Designing for Belonging: Why Student Wellness Starts with Space

    From walkable site planning to flexible interiors, intentional design choices play a critical role in how students experience comfort, connection, and community.

Digital Edition