Polished Floors, Right on Schedule

Students and faculty at the Southridge Elementary School in Casper, Wyoming were a bit shocked when they were informed that their brand new school would not be ready for the August 19 start of the school year. Many construction delays were encountered during the project, including the polished concrete floors in the school that were deemed unacceptable by the architect.

The building was 100-percent complete when the decision was made to completely repolish the entire school. Cove base was in place, walls were painted, carpet was laid and cabinets were set. The building was virtually ready to be occupied when the decision was made. A well-known concrete consulting company was hired to assess the situation. Their 20-page report indicated that the floor did not meet the standards of the specification and should be repolished and dyed to the architect’s specification.

Freddie Gwynn, owner of Polished Concrete of Wyoming sat down with the contracting superintendent of the project and discussed the potential remedy. “It’s not going to be cheap, but it will be right” Freddie told him. A rigid timetable to complete the work was laid out. In order to pull this off, Freddie brought in another highly qualified FGS Permashine Contractor, Shawn Weaver of Concrete Floor Systems based in Denver, Colorado.

Plastic was put into place floor to ceiling in order to minimize dust contamination and damaging the finished painted walls. The edging was perhaps the biggest task to tackle. Crews spent countless hours hand grinding and polishing right up to in place carpeting.

Care was taken to densify to complete rejection to ensure that the dye was properly locked in. Final polishing and further densification brought the entire building up to the specified 1500-grit level. What does the school think? “We are very pleased with our floors and with the two contractors,” exclaims Principal Rick Skatula.

This article originally appeared in the issue of .

Featured

  • Year-Round Schools Require Year-Round Indoor Air Quality Planning

    While many schools are out for the summer, year-round schools follow a more “balanced” schedule with shorter, more frequent breaks spaced throughout the school year. Even though this offers educational benefits, these facilities have less downtime for building maintenance. This can become an issue when facilities managers overlook the importance of routine HVAC maintenance and air duct cleaning services.

  • UCF Modernizes College of Hospitality Management

    The University of Central Florida in Orlando, Fla., recently completed a major renovation effort for the Rosen College of Hospitality Management, according to a news release. The project modernized 77,600 square feet worth of academic classrooms, teaching labs, and collaborative spaces to support both students and faculty.

  • ZeroEyes, Academic Innovators Partner to Provide Safety Solutions

    ZeroEyes, which produces a multi-analytics weapons detection and threat intelligence platform, recently announced a partnership with Academic Innovators, according to a news release.

  • nursing students talk while studying in a hallway

    Elsevier Launches VR Simulation Solution for Nursing Students

    Elsevier has introduced Shadow Health Lab with Virtual Reality, a simulation platform that allows nursing students to interact with virtual patients and build clinical judgment skills in a safe, realistic environment.