Cleaner Air is Safer Air

cleaner air

Vapor Mitigation Strategies’ team completed the piping from the vapor pits to the risers for the SSDS, installed the AVB, and installed four vapor monitoring wells to ensure there was no vapor intrusion at D.C. early childhood centers, ensuring student safety.

A national chain of early childhood education centers chose the location of its Washington D.C. project on property known to have soil and groundwater contamination left behind from its former uses. The building designers were cognizant of the potential for vapor intrusion risk which might present itself to a sensitive population and researched design options.

Their choice was to employ a vapor intrusion mitigation system, which included a combination of two elements: an active pump sub-slab depressurization system (SSDS) component, and a spray-applied asphaltic vapor barrier (AVB). The SSDS consists of two square subterranean concrete vault “pits” with slotted openings at the top, and piping running from the pits to risers penetrating the sub-floor.

Both vapor pits were installed as part of the General Contractor’s (GC) pre-vapor intrusion mitigation installation commitment to provide for large scale construction items prior to the finishing of the SSDS and AVB by vapor intrusion mitigation installation specialists.

The GC accomplished pre-installation work which included construction of the vapor pits, all plumbing and electrical penetrating uprights, concrete collars around clustered penetrating uprights, smooth-grinding of rough surfaces for attachment of AVB to the foundation, and constructed and compacted the sub-slab gravel bed.

Vapor Mitigation Strategies’ team completed the piping from the vapor pits to the risers for the SSDS, installed the AVB, and installed four vapor monitoring wells.

The AVB was installed using a three-layer approach. First, by applying a polypropylene tarp which was rolled out tailored to fit around the vertical uprights and sealed to the foundation or uprights with Geo-Seal.

After the tarp was completely rolled out and all uprights and edges were addressed and sealed, the core layer of Geo-Seal was sprayed over the entire area.

Then, a final layer of tarp was installed to provide protection to the vapor barrier itself since metal rebar and concrete were layered on top.

www.vapormitigationstrategies.com

This article originally appeared in the School Planning & Management February 2018 issue of Spaces4Learning.

Featured

  • College of the Desert Hits Construction Milestone on New Campus

    College of the Desert recently announced that the construction of its new Palm Springs Campus in Palm Springs, Calif., recently reached a major construction milestone, according to a news release. The college is partnering with general contractor C.W. Driver Companies, which recently “topped out” the facility by placing the final beam in its structure.

  • Deferred Maintenance Issues Growing at Universities, Gordian Reports

    U.S. colleges and universities are falling increasingly behind on facilities maintenance and repair, according to Gordian’s 13th annual State of Facilities in Higher Education report. The deferred capital renewal burden has reached $156 per gross square foot, an 8% increase over the previous year.

  • UT System Approves First Funds for New Campus

    The University of Texas System Board of Regents recently approved funds to build the first facility of a new campus in far west Fort Worth, Texas, according to university news. UTA West will serve as a branch of the University of Texas at Arlington and is scheduled to open in fall 2028.

  • Armstrong World Industries Acquires Parallel Architectural Products

    Armstrong World Industries, provider of interior and exterior architectural applications, recently announced that it has acquired the Colorado-based Parallel Architectural Products, according to a news release.