Cleaner Air is Safer Air

cleaner air

Vapor Mitigation Strategies’ team completed the piping from the vapor pits to the risers for the SSDS, installed the AVB, and installed four vapor monitoring wells to ensure there was no vapor intrusion at D.C. early childhood centers, ensuring student safety.

A national chain of early childhood education centers chose the location of its Washington D.C. project on property known to have soil and groundwater contamination left behind from its former uses. The building designers were cognizant of the potential for vapor intrusion risk which might present itself to a sensitive population and researched design options.

Their choice was to employ a vapor intrusion mitigation system, which included a combination of two elements: an active pump sub-slab depressurization system (SSDS) component, and a spray-applied asphaltic vapor barrier (AVB). The SSDS consists of two square subterranean concrete vault “pits” with slotted openings at the top, and piping running from the pits to risers penetrating the sub-floor.

Both vapor pits were installed as part of the General Contractor’s (GC) pre-vapor intrusion mitigation installation commitment to provide for large scale construction items prior to the finishing of the SSDS and AVB by vapor intrusion mitigation installation specialists.

The GC accomplished pre-installation work which included construction of the vapor pits, all plumbing and electrical penetrating uprights, concrete collars around clustered penetrating uprights, smooth-grinding of rough surfaces for attachment of AVB to the foundation, and constructed and compacted the sub-slab gravel bed.

Vapor Mitigation Strategies’ team completed the piping from the vapor pits to the risers for the SSDS, installed the AVB, and installed four vapor monitoring wells.

The AVB was installed using a three-layer approach. First, by applying a polypropylene tarp which was rolled out tailored to fit around the vertical uprights and sealed to the foundation or uprights with Geo-Seal.

After the tarp was completely rolled out and all uprights and edges were addressed and sealed, the core layer of Geo-Seal was sprayed over the entire area.

Then, a final layer of tarp was installed to provide protection to the vapor barrier itself since metal rebar and concrete were layered on top.

www.vapormitigationstrategies.com

This article originally appeared in the School Planning & Management February 2018 issue of Spaces4Learning.

Featured

  • Upcoming University of Alabama Performing Arts Center Hits Construction Milestone

    The University of Alabama in Tuscaloosa, Ala., recently celebrated the topping out of its new Smith Family Center for Performing Arts, according to a news release. The university is partnering with HPM for program and project management on the facility, which broke ground in 2023 and is scheduled for completion in November 2026.

  • UNL Kiewit Hall

    Designing for Engineering Excellence: Integrating Sustainability and Wellness at UNLs Kiewit Hall

    Kiewit Hall at the University of Nebraska-Lincoln exemplifies how academic institutions can integrate sustainability and wellness into modern learning environments. With an integrated and collaborative team approach, Kiewit Hall addresses enhanced learning and creativity, physical health, and mental wellness, and fosters a sense of community through innovative design, operations, and policy solutions.

  • classroom with crystal ball on top of a desk

    Call for Opinions: Spaces4Learning 2026 Predictions for Educational Facilities

    As 2025 winds to a close, the Spaces4Learning staff is asking its readers—school administrators, architects, engineers, facilities managers, builders, superintendents, designers, vendors, and more—to send us their predictions for educational facilities in 2026.

  • LSU Breaks Ground on $200M Residential Project

    Louisiana State University in Baton Rouge, La., recently broke ground on a new residential complex, according to university news. The South Quad residential project will consist of two buildings and add a total of 1,266 beds for freshmen students. The development comes with a price tag of $200 million, and it’s scheduled to open to students in fall 2027.

Digital Edition