New Texas High School Faces Rising Construction Costs

Construction on Frisco ISD’s newest high school began this summer amidst rising costs of building materials and labor shortages. These challenges led to a $13 million project increase for the newly named Emerson High School, putting the total to about $111.6 million, reported the Dallas Morning News.

Various factors contributed to the higher price tag of the school but one of the greatest factors is the state’s worker shortage due to immigration policies and lack of specialized workers. A recent survey from the Associated General Contractors of America found that about 80 percent of contractors nationwide reported difficulties finding craft workers to hire.

In addition, immigrants make up nearly half of the Dallas area’s jobs in construction, according to a new study by the New American Economy. But latest immigration policies have contributed to a shortage of workers. Due to Frisco’s rapid growth, the school has had to compete for workers against other construction industries.

The rising cost of materials, like lumber and steel, impacted the 14 percent increase of the school as well, a spokeswoman for Frisco ISD told Dallas Morning News. The district also tacked on about $4 million worth of additional features that weren’t in the original school plans, including synthetic turf athletic fields, a paved marching band field and security features.

Emerson High School is funded through the 2014 bond program and set to be completed in 2021.

About the Author

Yvonne Marquez is senior editor of Spaces4Learning. She can be reached at [email protected].

Featured

  • Texas K–12 District to Build New Elementary, High Schools

    The High Island Independent School District on the Bolivar Peninsula in Southeast Texas recently announced that construction on a new elementary school and a new high school will begin in January 2026, according to local news. Funding will come from a $27.9-million bond passed in May 2025.

  • Upcoming University of Alabama Performing Arts Center Hits Construction Milestone

    The University of Alabama in Tuscaloosa, Ala., recently celebrated the topping out of its new Smith Family Center for Performing Arts, according to a news release. The university is partnering with HPM for program and project management on the facility, which broke ground in 2023 and is scheduled for completion in November 2026.

  • Longwood University Selects Builder for $73M Performing Arts Center

    Longwood University in Farmville, Va., recently announced that it has selected Swedish construction company Skanska as the builder of its new performing arts center, according to online news. The project involves the demolition of the current building and constructing a new, 64,500-square-foot facility.

  • South Texas K–12 District Debuts Region’s First Electric Bus Fleet

    The Valley View Independent School District in Pharr, Texas, recently announced a partnership with Highland Electric Fleets to launch the district’s—and the region’s—first fleet of all-electric school buses, according to a news release.

Digital Edition