High-School Construction to Finish Early, Under Budget Due to COVID

Construction work on Hendersonville High School, located in Hendersonville, N.C., is set for completion in August 2022—11 months ahead of schedule. The project will also come in about half a million dollars under its $59.1-million budget.

Henderson County Capital Projects Manager David Berry attributes the accelerated timeline to sitework during the summer before construction, as well as a reduced student presence in the school due to the COVID-19 pandemic that allowed workers more and longer access to the site. He announced the news to the Board of Commissioners, who voted to amend its contract with Vannoy Construction to incorporate the new schedule and financial information.

“This is, for me, exciting news to bring forward to this board,” said Berry. “This whole project has been not only the most expensive that Henderson County—I believe—has taken on; it’s been the most difficult. And without everybody’s cooperation, we wouldn’t be where we are.”

The project includes renovations to two campus buildings (the Stillwell Building and the gymnasium completed in 1974) as well as a new-two story building. The new building will play home to administrative offices; a student media center; a new cafeteria; and new science, chorus, and band classrooms. The new building is set to open in August 2021 instead of its original December 2021 completion date.

“Students are going to benefit from this,” said Henderson County Public Schools Superintendent John Bryant. “Taxpayers are going to benefit from this. While logistical challenges will be presented, we welcome those challenges. We know that we’ll be successful in meeting those challenges because they benefit the children of our community.”

About the Author

Matt Jones is senior editor of Spaces4Learning. He can be reached at [email protected].

Featured

  • University of Tennessee at Chattanooga Launches New Emergency Communications System

    The University of Tennessee at Chattanooga (UTC) recently deployed a new emergency notification and incident management system for its campus, according to a news release. The university partnered with 911Cellular to launch Safe@UTC, a smartphone app allowing university officials to communicate and respond during emergency situations.

  • Spaces4Learning Trends & Predictions for Educational Facilities in 2026: Part II

    As education leaders look toward 2026, the design of K–12 and higher education facilities is being reshaped by powerful, converging forces. Survey respondents point to the rapid growth of Career and Technical Education, deeper alignment with workforce and industry needs, and the accelerating influence of AI and emerging technologies.

  • University of Arizona Approves New Residence Hall

    The Arizona Board of Regents recently approved plans for a new residence hall at the University of Arizona in Tucson, Ariz., according to a news release. The new facility is scheduled to open in fall 2028 and have the capacity for more than 1,200 students, enforcing a new university expectation that all first-year students live on campus.

  • How a Portable Sink Helped an Art Classroom Run More Smoothly

    Classroom design decisions can have outsized effects on instructional time and safety at schools juggling mismatched infrastructure, strict budgets, and crowded schedules — particularly in the arts. Between spilled paint and dirty brushes, art classes run smoother with a sink in the studio. But many schools don’t have a sink in every art classroom.