District Presses Pause on $13M in Construction Projects

The St. Clair R-XIII School District in St. Clair, Mo., announced last week that it will delay several planned construction projects due to a spike in the cost of materials. The school board voted on Thursday, June 10, to pause the wheels of construction on a bus bay ($1.644 million), a new auditorium ($11-12 million), and a pickup and drop-off loop ($340,000).

At the board meeting, members cited the example of lumber costs. A two-by-four was slated to cost $14, while members recalled the same product costing between $2 and $5 during previous, personal home renovation projects.

Other projects will continue, including the installation of a $444,000 safety vestibule in the elementary and junior high schools; and renovations at St. Clair Junior High consisting of a handicap-accessible toilet stall to a women’s restroom ($27,500); a family restroom ($28,200); and installing $3,500 in vestibule carpeting. Work will also continue on projects already in progress, including a $413,000 track and a $386,000 grandstand.

All of the above projects, both those slated to continue and those that have been delayed, were intended to be funded by a $12.75 million bond issue that voters passed in June 2020.

“I want to pause on a lot of things,” said district superintendent Dr. Kyle Kruse. “I have a hard time really wanting to pause on safety.”

According to the original terms of the bond issue agreement, the money must be spent within three years of receiving it. The bond issuer, LJ Hart & Co., has said that it will consider extending the deadline under reasonable circumstances. The school board said at its June 2 meeting that it will return to the delayed projects “in a few months” to price-check construction materials.

About the Author

Matt Jones is senior editor of Spaces4Learning. He can be reached at [email protected].

Featured

  • University of Southern Mississippi Starts Construction on Oyster Hatchery

    The University of Southern Mississippi (USM) recently announced that construction has begun on a new oyster hatchery at its Gulf Coast Research Laboratory (GCRL) Thad Cochran Marine Aquaculture Center (TCMAC) Cedar Point campus in Ocean Springs, Miss., according to a news release.

  • Construction Begins on East Austin CTE-Focused High School

    The Del Valle Independent School District recently announced that construction has begun on a new CTE-focused high school in Austin, Texas, according to a news release. Del Valle High School will measure in at 473,338 square feet and have the capacity for 2,400 students.

  • ed tech conference calendar

    Upcoming Awards, Events & Webinars

  • KI Launches K–12 Classroom Furniture Giveaway

    Contract furniture company KI recently announced the launch of its fourth-annual Classroom Furniture Giveaway, which awards $50,000 each to four K–12 educators across the U.S., according to a news release. The goal is to address decreasing student engagement and increasing teacher burnout numbers by updating learning spaces to accommodate modern needs.

Digital Edition