Construction Delays Opening of Ky. Middle School

When school starts on Thursday, Aug. 12, students of East Hardin Middle School in Hardin County, Ky., will return to their old building instead of a brand-new facility as originally expected. Officials say construction problems and electrical issues have resulted in the postponement of the new building’s grand opening. Students were originally supposed to make the move in January before COVID-related complications pushed the date to August. Now, the opening has been delayed again.

“We’ve ran into some electrical issues and just haven’t been able to get where we wanted to be,” said John Wright, Hardin County Schools spokesperson.

Alliance Corp. CEO Tommy Gumm cites a current “inability” to complete the work, failing to meet promised deadlines, and delays in finishing aspects like fire alarm systems on the part of the electric company. Likewise, Hardin County Schools (HCS) Chief Operations Officer John Stith said that the deadline of completing the fire alarm system was missed, which pushed the work to a minimum of a week behind schedule. He also cited delays that came earlier in the process, like masonry work.

On Aug. 1, the HCS Board of Education approved a temporary virtual learning option for East Hardin Students. Later that week, the district announced that in-person instruction would be available at the school’s old location.

“The thoughts of those involved with the construction today [Tuesday, Aug. 3] confirmed our fears about a timely certification of occupancy,” said HCS Superintendent Teresa Morgan. “What we heard today means that virtual instruction would’ve taken place for possibly longer than a month. We had hoped the virtual instruction would not last longer than seven days, and we’d be able to transition into the new building. Any construction project, especially one as large as a new school building, always brings variables and uncertainties.”

Officials have not yet provided an updated timeline on when the $24-million building will be ready for students. “It’s just really uncertain right now,” said Wright. Morgan agreed that the district will communicate with families regarding the building’s opening.

About the Author

Matt Jones is senior editor of Spaces4Learning. He can be reached at [email protected].

Featured

  • K–12 Safety Trends Report Reveals Reliance on Training, Technology

    Wearable safety technology provider CENTEGIX recently released its 2025 School Safety Trends Report, according to a news release. The report is based on more than 265,000 incidents during the 2024–25 school year as reported through the CENTEGIX Safety Platform, used by more than 800 school districts across the U.S.

  • Kraus-Anderson Continues Work in Minnesota School District

    Maple River Schools in Mapleton, Minn., recently began construction on another project included in a district long-range facilities plan. Construction management firm Kraus-Anderson recently began work on two new classrooms and an outdoor track and field facility, according to a news release.

  • Designing Learning Spaces that Support Student Mental Health and Wellness

    In today’s education landscape, schools are more than just centers for learning; they are integral to the holistic development and well-being of students. The global pandemic underscored the importance of addressing mental health in schools, as productivity dropped, stress levels rose and students faced challenges managing emotions.

  • KI Wall Demonstrates New Solutions at NeoCon 2025

    KI Wall attended NeoCon 2025 in Chicago, Ill., last month to showcase its new architectural wall systems and collaborations, according to a news release. Its customizable, design-forward wall solutions are intended to support creativity in work, education, and healthcare environments.

Digital Edition