Construction Delays First Day of Classes at Nebraska Elementary School

Ada Robinson Elementary School in Lincoln, Neb., had its first day of school on Monday, August 29—two weeks later than planned. The newly built elementary school was originally scheduled to open its doors to students on August 15, but construction delays forced the district to reconsider, according to local news.

On Friday, August 5, just hours after a media tour of the new facility, Superintendent Paul Gausman sent a letter to parents announcing the decision. “Out of an abundance of caution, I do not feel we will be ready to safely open the school building to students on August 15,” he said in the letter. “In order to ensure the safety of all our staff and students, we need to allow the construction team extra time to finish the core areas.”

One wing of the school is still under construction even after the building’s opening, as well as the playground and an open outdoor grassy area, local news reports. These final projects were always intended to continue through the fall, said Lincoln Public Schools.

“We knew when the project started that Robinson always faced a tight and challenging construction timeline amid a global pandemic which caused supply chain challenges and labor shortages,” said Gausman.

The district also announced that, in order to make up the lost time and meet instructional time requirements, the school day will be extended by 17 minutes for the remainder of the school year. Also, it will not offer an early release for the first week of school, unlike all the other schools in the district.

The new facility covers about 85,000 square feet and has capacity for 528 students, according to the district website. About 290 students are projected to attend during the first year. The PreK–5 facility was named after longtime respected district teacher Ada Robinson, who surprised students and staff on the first day of school to welcome them to their new home.

About the Author

Matt Jones is senior editor of Spaces4Learning. He can be reached at [email protected].

Featured

  • Kimball Showroom Earns WELL Certified Platinum Distinction

    Commercial furnishings company Kimball International recently announced that its showroom in New York City has achieved WELL Certification at the Platinum level as dictated by the International WELL Building Institute, according to a news release. The certification demonstrates a continuing commitment to creating environments that promote health, well-being, and productivity.

  • California K–12 District Opens New Athletic Complex, Gym

    The San Mateo Union High School District (SMUHSD) in San Mateo, Calif., recently announced the completion of two new athletics facilities: a new gymnasium at Burlingame High School, and a new athletic training complex at San Mateo High School, according to a news release.

  • KI Wall Demonstrates New Solutions at NeoCon 2025

    KI Wall attended NeoCon 2025 in Chicago, Ill., last month to showcase its new architectural wall systems and collaborations, according to a news release. Its customizable, design-forward wall solutions are intended to support creativity in work, education, and healthcare environments.

  • StarRez Releases 2025 State of Student Housing Report

    Student housing software solutions provider StarRez recently released its second State of the Student Housing Industry Report, according to a news release. The report is based on the results of survey data from more than 400 higher education institutions around the world, both StarRez clients and not.

Digital Edition