Before Renovations Begin, Iowa Middle School Schedules Asbestos Abatement

The Perry School Board of Perry, Iowa, is still accepting construction bids for its $10 million renovation project of Perry Middle School. Before the renovations can begin, the school is pursuing a month-long asbestos abatement project. School Board President Kyle Baxter attributes the reluctance of contractors to submit bids to the renovation project’s tight turnaround time once that abatement is finished.

The asbestos-related work is slated to begin on May 1. In February, the school board’s request to conduct Perry Middle School’s classes remotely for the month of May was denied. Instead, the middle school and Perry High School principals have worked out a plan to hold in-person classes for middle school students at the high school. The whole sixth grade class will set up shop in the PHS multipurpose room. Seventh and eighth grade students will be placed in various empty classrooms throughout the school.

“The reason that we need that month, that four weeks, is that they are saying that abatement is supposed to take four weeks, which would push the project well into September,” said PCSD Superintendent Clark Wicks. “I think it’s better to put that delay—or whatever you want to call it, that virtual piece—in May and start the school year clean. So that is still our goal.”

The students’ last day in the middle school is set for April 23. Movers will come through and clear out the building—removing furniture, projectors, hot spots, and so on—so that the asbestos abatement can begin on May 1.

Perry Middle School Principal Shaun Kruger thanked the PHS principal, as well as his own school’s faculty and students, for their flexibility during the abatement and subsequent renovations. “I’m proud of them,” Kruger said. “They’ve embraced it. They’ve got some multidisciplinary units with the whole group and some other neat ideas planned, and are taking advantage of the opportunity.”

Renovations are scheduled to be completed by the beginning of next school year. “I know there’s some [general contractors] who are interested and asking questions,” said Baxter. “We lost a month of instruction, so part of what we had to do was extend into the fall, so we may be creative in what we have to do over there. Hopefully, we can still get started here in spring break with asbestos and get that rolling.”

Planned renovations for the middle school include expanded and relocated classrooms; updated furniture like student desks, chairs, and classroom fixtures; a new computer lab and STEM lab; new wiring and electrical equipment; updated projectors; and new lighting and ceilings throughout the entire building.

About the Author

Matt Jones is senior editor of Spaces4Learning. He can be reached at [email protected].

Featured

  • Fayetteville State University Opens New Residence Hall

    Fayetteville State University (FSU) in Fayetteville, N.C., recently completed construction on a new $50-million residence hall, according to a news release. The university partnered with KWK/Jenkins • Peer Architects on the design of Bronco Pride Hall.

  • ClassVR Wins Tech & Learning Best of Show at ISTELive 25

    Avantis Education recently announced that its flagship product, ClassVR, won the Tech & Learning Best of Show Award at ISTELive 25 in San Antonio, Texas, according to a news release. The program is designed to celebrate products that are “transforming education in schools around the world and that show the greatest promise for the industry,” and this is the fourth consecutive year that Avantis has claimed the award.

  • ALAS Announces 2025–26 Award Winners

    The Association of Latino Administrators and Superintendents (ALAS) recently announced the winners of its 2025–26 leadership awards, according to a news release. Winners will be recognized at the ALAS 22nd National Summit on Education, scheduled for Oct. 15–17 in Chicago, Ill.

  • Upcoming University of Alabama Performing Arts Center Hits Construction Milestone

    The University of Alabama in Tuscaloosa, Ala., recently celebrated the topping out of its new Smith Family Center for Performing Arts, according to a news release. The university is partnering with HPM for program and project management on the facility, which broke ground in 2023 and is scheduled for completion in November 2026.

Digital Edition