High-School Construction to Finish Early, Under Budget Due to COVID

Construction work on Hendersonville High School, located in Hendersonville, N.C., is set for completion in August 2022—11 months ahead of schedule. The project will also come in about half a million dollars under its $59.1-million budget.

Henderson County Capital Projects Manager David Berry attributes the accelerated timeline to sitework during the summer before construction, as well as a reduced student presence in the school due to the COVID-19 pandemic that allowed workers more and longer access to the site. He announced the news to the Board of Commissioners, who voted to amend its contract with Vannoy Construction to incorporate the new schedule and financial information.

“This is, for me, exciting news to bring forward to this board,” said Berry. “This whole project has been not only the most expensive that Henderson County—I believe—has taken on; it’s been the most difficult. And without everybody’s cooperation, we wouldn’t be where we are.”

The project includes renovations to two campus buildings (the Stillwell Building and the gymnasium completed in 1974) as well as a new-two story building. The new building will play home to administrative offices; a student media center; a new cafeteria; and new science, chorus, and band classrooms. The new building is set to open in August 2021 instead of its original December 2021 completion date.

“Students are going to benefit from this,” said Henderson County Public Schools Superintendent John Bryant. “Taxpayers are going to benefit from this. While logistical challenges will be presented, we welcome those challenges. We know that we’ll be successful in meeting those challenges because they benefit the children of our community.”

About the Author

Matt Jones is senior editor of Spaces4Learning. He can be reached at [email protected].

Featured

  • Epson Receives Seven AV Industry Awards

    Projectors manufacturer Epson recently announced that it received multiple awards across the Higher Ed AV Awards, SCN Stellar Service Awards, and InfoComm 2025, according to a news release. The company was recognized for three projectors from its PowerLite L-Series line, accessories, installation process, and its customer support team.

  • Photo courtesy of Spiezle Architectural Group, Inc.

    West Melbourne School for Science Completes Expansion Project

    The West Melbourne School for Science, which serves students grades PreK–6 in West Melbourne, Fla., recently completed a 12,450-square-foot elementary school expansion, according to a news release.

  • Ancient Resilience: How Indigenous Intelligence Shapes the 4Roots Education Building

    As climate change intensifies, educational spaces must evolve beyond basic sustainability toward true resilience – we must design environments that can adapt, respond, and thrive amid shifting, and intensifying, climate hazards. Drawing on indigenous wisdom and nature-based strategies, integrating resilient design offers a path to create learning environments that are not only functional but deeply in tune with their natural surroundings.

  • Case Study Highlights Texas District’s Campus Security Upgrades

    The Taft Independent School District near Corpus Christi, Texas, recently partnered with Intech Southwest Services to revamp its campus security technology system, according to a news release. Intech has released a case study on its website detailing the process that advanced the district’s technology by more than 20 years in less than three weeks.

Digital Edition