Kentucky District Delays Start of School Following Construction Delays

The Hopkins County Board of Education in Madisonville, Ky., recently announced that it will push back the start date of the 2023–24 academic year based on construction delays at a new elementary school, according to local news. The district’s first day of school will move from August 9 to August 15 to accommodate construction at a replacement facility for Hanson Elementary School.

According to board members, the project was originally scheduled for completion in 2022 and has faced delays throughout the process. The school partnered with A & K Construction, who district officials say aren’t delivering what they promised, according to local news.

“You’ve put us in a position that we’re going to have to make an adjustment,” said Board Chairman Shannon Embry to A & K President Bill Boyd at a recent school board meeting.

“I am praying and hoping that you are a man true to your word,” said Superintendent Amy Smith to Boyd at the same meeting. “[I’m praying] that that date of completion will not be moved and we can look at our community and welcome our babies into their schools on August 15.”

Smith also said that Boyd has promised that the school’s interior will be completed by July 27 and other site work—like bus and car lanes—by August 7.

Smith also clarified that the purpose of moving the date was not to give the construction company additional leeway, but to give school staff the time to set up their classrooms properly before students arrive.

”We have based our decisions on the deadlines they’ve given us,” Smith said. “We are not the ones that are completing the construction. We rely on them—the experts—to be able to be able to do that and to give us a date and live by that.”

About the Author

Matt Jones is senior editor of Spaces4Learning. He can be reached at [email protected].

Featured

  • CU-Lock Haven Receives $1.75M Gift for New Entrepreneurship, Media Center

    Commonwealth University-Lock Haven in Lock Haven, Penn., recently received a $1.75-million donation from entrepreneur and alumnus Nicholas Subich ’17, according to a university news release. The funds will go toward establishing the Nicholas Subich Center for Entrepreneurship and Media, a technology-driven hub for innovation and experiential learning.

  • UT-San Antonio Begins Residence Hall Renovations

    The University of Texas at San Antonio recently began a $6-million renovation project to one of its residence halls, according to a news release. Originally completed in 1986, Chisolm Hall measures in at 120,860 square feet and is the oldest and largest residence hall on campus.

  • Cal Poly Humboldt Starts Construction on Healthcare Education Hub

    California State Polytechnic University, Humboldt in Arcata, Calif., recently announced that work has begun on a renovation project that will turn the Stewart Building into a new Healthcare Education Hub, according to a news release. The university is partnering with Sundt Construction Inc. for construction services.

  • How Proactive Maintenance Can Transform Athletic Facilities into Strategic Assets for College Sports

    College athletics is entering one of the most transformative periods in its history. With NIL reshaping financial models and competitive expectations, athletic departments across the country are being asked to do more than ever with increasingly constrained resources.