Managing Delays From the Construction Side

Not all construction delays are the fault of the construction contractor. By keeping the lines of communications open, the client and contractor together can work to avoid any serious slowdowns in the project.

Project managers should be aware of early warning of delays caused by the client, main contractor or your own people. Client delays arise because they may change their minds, give instructions too late or are slow in approving drawings and plans. They tend to overlook the fact that these delays push back the start for contractors or sub-contractors, and that the contractor is powerless to avoid these delays.

Main contractor delays usually involve construction work being completed late, causing subsequent stages to fall behind schedule. In some cases, delays are the result of mismanagement and a lack of coordination.

Last but not least, the subcontractors themselves may cause delays; for example, by under-resourcing the project in the early stages or by not completing design drawings and getting them approved on time.

Make sure delays outside your control are recognized and documented. Such delays can impact you financially and need to be recorded and the financial impact dealt with by the responsible party. You should not have to bear the cost of other peoples’ delays, nor should you be blamed for them.

This article originally appeared in the issue of .

Featured

  • Fellowes Launches New 3D Modular, Product Configurators

    Contract interiors and architectural solutions provider Fellowes recently announced the launch of new 3D modular and product configurators for several of its product lines, according to a news release. The new products offer SIF file integration and pricing for the Volo, Markerboards, Sena, and Rising product lines in connection with 3D Cloud, which provides 3D product visualization and 3D digital asset management.

  • North Dakota State University Completes Music School Renovation

    North Dakota State University in Fargo, N.D., recently announced that construction on the Challey School of Music has finished, according to a news release. The university partnered with Foss Architecture & Interiors for design and Kraus-Anderson for construction services, and construction began in July 2024.

  • California High School Starts Construction on STEAM, Music Buildings

    Tamalpais High School, part of the Tamalpais Union High School District, recently broke ground on two new major facilities for its campus in Mill Valley, Calif., according to a news release. The district is partnering with Quattrocchi Kwok Architects (QKA) and Lathrop Construction Associates for the Science Technology, Engineering, Arts, and Mathematics (STEAM) and Music Buildings, both replacing their outdated counterparts.

  • Average Annual Number of Tornadoes per State

    New Tornado Wind Load Design Criteria in IBC Offer Improvements to Life Safety

    For the first time in U.S. building code history, the 2024 International Building Code (IBC) includes tornado wind load design criteria, marking a significant advancement in life-safety provisions.