New Jersey Schools Development Authority Announces Success of Program Overhaul

Design-Build Approach Shows Benefits to Budget and Schedule

Trenton, N.J. – At yesterday’s monthly board meeting of the New Jersey Schools Development Authority (NJSDA), NJSDA Board Members were provided with an update regarding the success of new processes and approaches implemented under the Christie Administration. The presentation focused on 12 projects that have been approved as part of the NJSDA’s Capital Project Portfolio. Of the projects studied, all projects were completed within or under budget.  Eleven of the projects were delivered either before or as originally projected including four that were delivered ahead of schedule.

“The positive results shared today were achieved through the significant programmatic and organizational changes instituted at the NJSDA under the Christie Administration,” said NJSDA CEO Charles McKenna. “Our record of routinely completing construction projects within anticipated budget and timelines highlights the success of the State’s school construction program. We are getting it right here in New Jersey.”

Another significant benchmark examined was the total change orders experienced on the projects reviewed. The 12 projects evaluated experienced an average of 2.2 percent in change orders per project. Those built through the design-build approach, the method currently most utilized by the NJSDA, experienced an average of only 0.5 percent in change orders per project. In comparison, prior to the Christie Administration (from 2006 to 2009), construction contracts for 17 projects that received a notice to proceed experienced an average of nearly 12.2 percent in change orders. That equates to a savings of more than $2 million per project on average compared to portfolio projects completed in prior years.

“NJSDA’s use of the design-build approach and an expanded constructability review process has resulted in fewer schedule delays and change orders,” said NJSDA Chairman Edward Walsh. “These significant accomplishments highlight the NJSDA’s proficiency in the management and construction of school facilities projects throughout New Jersey. The Authority is delivering efficiently designed, high-quality educational facilities that best meet the needs of New Jersey’s students while ensuring proper management of taxpayers’ resources.”

Seven of the 12 projects completed utilized the design-build approach, which differs from the traditional method in that NJSDA contracts with one firm for both design and construction of a school facilities project. This approach also allows for some design and construction activities to proceed concurrently through phased advancement, which has been found to improve upon project timelines.

For the remaining five projects advanced through the design-bid-build approach, the NJSDA implemented an enhanced constructability review process. The Constructability Review provides a contractor with an opportunity to analyze the contract documents (plans and specifications) to identify any issues that would impact the schedule or cost of completion, so that such issues can be resolved before commencement of construction. Through this process, NJSDA has experienced a substantial reduction in unforeseen issues, schedule delays and change orders.

The SDA manages the design and construction of school facilities projects in New Jersey’s 31 SDA Districts. The SDA is responsible for financing 100 percent of the cost of school facilities projects in SDA Districts. The SDA also provides grants of at least 40 percent of the eligible costs to New Jersey’s Regular Operating Districts. The SDA’s current portfolio of active projects is valued at $2 billion – including the Capital Project Portfolio, emergent projects, and Regular Operating District grants.

Featured

  • Texas District Finishes Construction on New Middle School, Admin Building

    The Westwood Independent School District recently held a ribbon-cutting ceremony for the new Westwood Middle School and Administration Building in Palestine, Texas, according to a news release. The campus covers 106,000 square feet and has the capacity for 650 students in grades 6–8, and it will also play home to the district’s staff and administration.

  • Texas State University Completes Stadium Renovations

    Texas State University in San Marcos, Texas, recently announced that it has completed a series of additions and renovations to its football stadium, according to a news release. Formerly known as the Bobcat Stadium End Zone Complex, the Johnny and Nathali Weisman Football Performance Center is an 85,000-square-foot expansion featuring hospitality spaces, banquet spaces, exterior concourses, and upgrades to the field house.

  • Florida SouthWestern State College, Skanska Partner for Humanities Hall Renovation

    Florida SouthWestern State College (FSW) in Fort Myers, Fla., recently announced that it is partnering with construction firm Skanska to renovate the school’s Humanities Hall, according to a news release.

  • iPark 87

    Building a Future-Focused Career and Technical Education Center

    A district superintendent shares his team's journey to aligning student passions with workforce demands, and why their new CTE center could be a model for districts nationwide.

Digital Edition