Binghamton U Puts Most Construction on Hold During Virus Closures

Directions issued by Gov. Andrew Cuomo in late March suspended all non-essential construction activity in New York, leaving universities and colleges scrambling to put construction projects on hold in a manner that would allow them to pick up the work when closures have been lifted. At Binghamton University, part of the State University of New York system, that affected numerous building sites.

One of the largest projects, an addition to the Hinman Dining Hall, needed to have utility tie-ins done for safe shutdown, after almost all of the utilities — telecom, electrical, water and sewer — were relocated.

A chiller project underway in a science building had to continue long enough to ensure the appropriate building systems were in place to protect the buildings with HVAC.

Work was simply stopped in other projects, including a renovation to the Decker College of Nursing and Health Sciences; upgrades to the Engineering Building; interior work for another science building; and renovation of a residence hall.

"This suspension obviously affects project schedules and completion dates, but it is too soon to gauge the impact," a missive from Physical Facilities stated.

The same statement said that some construction work would continue. That encompasses projects designated as "critical infrastructure," including work at hospitals or healthcare facilities, affordable housing and homeless shelters.

SUNY issued contractor guidance for its construction jobsites, which offered a number of recommendations for workers, including having fellow workers informed when employees are confirmed to have COVID-19, performing "social distancing" on the job site, encouraging "hand hygiene," staggering work schedules to minimize how many people are at a job site at any one time and avoiding "cleaning techniques, such as pressurized air or water sprays that may result in generation of bioaerosols."

New York state has suffered the greatest number of COVID-19 cases (90,020 as of May 18, 2020) and deaths (28,339) of any state in the country.

About the Author

Dian Schaffhauser is a former senior contributing editor for 1105 Media's education publications THE Journal, Campus Technology and Spaces4Learning.

Featured

  • Minnesota Middle School Finishes $23.5M Addition and Modernization

    Highland Park Middle School in St. Paul, Minn., recently announced the completion of a $23.5-million addition and remodel project, according to a news release. Saint Paul Public Schools partnered with ATS&R Planners, Architects & Engineers for its design and Kraus-Anderson for its construction.

  • University of Kansas Opens $400M Football Stadium Reconstruction

    The University of Kansas in Lawrence, Kan., recently announced that the $400-million reconstruction of David Booth Kansas Memorial Stadium is complete in time for the 2025 football season, according to a news release. The university partnered with Turner Construction Company on the project.

  • Armstrong World Industries Acquires Geometrik

    Armstrong World Industries, designer and manufacturer of interior and exterior architectural applications like ceilings, walls, and metal solutions, recently announced its acquisition of Canada-based Geometrik, according to a news release. The British Columbian Geometrik specializes in designing and manufacturing wood acoustical and wall systems.

  • classroom with crystal ball on top of a desk

    Call for Opinions: Spaces4Learning 2026 Predictions for Educational Facilities

    As 2025 winds to a close, the Spaces4Learning staff is asking its readers—school administrators, architects, engineers, facilities managers, builders, superintendents, designers, vendors, and more—to send us their predictions for educational facilities in 2026.

Digital Edition