High-School Construction to Finish Early, Under Budget Due to COVID

Construction work on Hendersonville High School, located in Hendersonville, N.C., is set for completion in August 2022—11 months ahead of schedule. The project will also come in about half a million dollars under its $59.1-million budget.

Henderson County Capital Projects Manager David Berry attributes the accelerated timeline to sitework during the summer before construction, as well as a reduced student presence in the school due to the COVID-19 pandemic that allowed workers more and longer access to the site. He announced the news to the Board of Commissioners, who voted to amend its contract with Vannoy Construction to incorporate the new schedule and financial information.

“This is, for me, exciting news to bring forward to this board,” said Berry. “This whole project has been not only the most expensive that Henderson County—I believe—has taken on; it’s been the most difficult. And without everybody’s cooperation, we wouldn’t be where we are.”

The project includes renovations to two campus buildings (the Stillwell Building and the gymnasium completed in 1974) as well as a new-two story building. The new building will play home to administrative offices; a student media center; a new cafeteria; and new science, chorus, and band classrooms. The new building is set to open in August 2021 instead of its original December 2021 completion date.

“Students are going to benefit from this,” said Henderson County Public Schools Superintendent John Bryant. “Taxpayers are going to benefit from this. While logistical challenges will be presented, we welcome those challenges. We know that we’ll be successful in meeting those challenges because they benefit the children of our community.”

About the Author

Matt Jones is senior editor of Spaces4Learning. He can be reached at [email protected].

Featured

  • El Paso District Breaks Ground on New Elementary School

    The Canutillo Independent School District in El Paso, Texas, recently announced that construction has begun on a 119,000-square-foot elementary school, according to a news release. The district partnered with Pfluger Architects, Carl Daniel Architects, and LDCM Solutions on the new Davenport Elementary School, which has an expected completion date of 2027.

  • Countway Library at Harvard Medical School

    From Shadows to Sanctuary: The Transformation of Light at Countway Library

    The renovation of Countway Library at Harvard Medical School demonstrates how biophilic design and advanced lighting strategies transformed a formerly dark, insular space into a vibrant, welcoming hub that supports wellness, learning, and community engagement.

  • Massachusetts K–12 District Selects Architect for New Junior High

    Swansea Public Schools in Swansea, Mass., recently announced that it has selected Finegold Alexander Architects to design a new junior high school for the district, according to a news release. The firm will create the Feasibility Study and Schematic Design for Joseph Case Junior High School after a lengthy selection process by the Massachusetts School Building Authority (MSBA).

  • UT System Board of Regents Approves $108M Housing Complex

    The University of Texas System Board of Regents recently announced the approval of a new, $108-million housing complex at the University of Texas at El Paso (UTEP), according to a news release. The facility will stand four stories and have a total of 456 new beds for freshmen students.

Digital Edition