Construction Delays Opening of Ky. Middle School

When school starts on Thursday, Aug. 12, students of East Hardin Middle School in Hardin County, Ky., will return to their old building instead of a brand-new facility as originally expected. Officials say construction problems and electrical issues have resulted in the postponement of the new building’s grand opening. Students were originally supposed to make the move in January before COVID-related complications pushed the date to August. Now, the opening has been delayed again.

“We’ve ran into some electrical issues and just haven’t been able to get where we wanted to be,” said John Wright, Hardin County Schools spokesperson.

Alliance Corp. CEO Tommy Gumm cites a current “inability” to complete the work, failing to meet promised deadlines, and delays in finishing aspects like fire alarm systems on the part of the electric company. Likewise, Hardin County Schools (HCS) Chief Operations Officer John Stith said that the deadline of completing the fire alarm system was missed, which pushed the work to a minimum of a week behind schedule. He also cited delays that came earlier in the process, like masonry work.

On Aug. 1, the HCS Board of Education approved a temporary virtual learning option for East Hardin Students. Later that week, the district announced that in-person instruction would be available at the school’s old location.

“The thoughts of those involved with the construction today [Tuesday, Aug. 3] confirmed our fears about a timely certification of occupancy,” said HCS Superintendent Teresa Morgan. “What we heard today means that virtual instruction would’ve taken place for possibly longer than a month. We had hoped the virtual instruction would not last longer than seven days, and we’d be able to transition into the new building. Any construction project, especially one as large as a new school building, always brings variables and uncertainties.”

Officials have not yet provided an updated timeline on when the $24-million building will be ready for students. “It’s just really uncertain right now,” said Wright. Morgan agreed that the district will communicate with families regarding the building’s opening.

About the Author

Matt Jones is senior editor of Spaces4Learning. He can be reached at [email protected].

Featured

  • Rhode Island Boarding School Completes Student Dorm Renovations

    St. George’s School in Middletown, R.I., recently announced the completion of a $26-million renovation project on Arden-Diman-Eccles Dormitory, according to a news release. The school partnered with Voith & Mactavish Architects (VMA) on the new space, which places a new focus on collaborative community spaces open to both boarding students and day students.

  • North Carolina District Completes New Elementary School

    The Wake County Public School System (WCPSS) in Holly Springs, N.C., recently announced that construction on a new elementary school has finished, according to a news release. Rex Road Elementary School measures in at 133,000 square feet and is the fifteenth school that general contractor Balfour Beatty has completed for the district.

  • Minnesota Middle School Finishes $23.5M Addition and Modernization

    Highland Park Middle School in St. Paul, Minn., recently announced the completion of a $23.5-million addition and remodel project, according to a news release. Saint Paul Public Schools partnered with ATS&R Planners, Architects & Engineers for its design and Kraus-Anderson for its construction.

  • Houston-Area High School Breaks Ground on 117,000SF Multi-Use Facility

    North Shore Senior High School, part of Galena Park ISD in Houston, Texas, recently broke ground on a new multi-use facility for student extracurriculars, according to a news release. The North Shore Multi-Use Facility will include dedicated practice and training space for the school’s athletics and fine arts programs.