Flooring Installation

Concrete slabs are the most common flooring base used in a range of buildings, including schools. Unfortunately, excessive moisture found in concrete slabs prior to a flooring installation can cause significant floor covering system failures such as debonding of coatings, microbial growth and flooring expansion.

There are, however, several steps that can be taken to mitigate and potentially prevent moisture issues before a floor covering is installed. These steps can be taken for either new or remodel projects.

The first step is to conduct moisture testing. Substrate surfaces must be tested for moisture emission prior to starting the installation. Most manufacturers and flooring installation contractors recommend Relative Humidity probe moisture testing.

If moisture emission is discovered, then proper precautions, such as the use of several topical applications prior to the flooring installation, can be used for moisture mitigation. Some of these topical applications include using reactive penetrants and moisture retarding coatings.

Finally, consider selecting a floor covering that has a higher tolerance for moisture and can perform in concrete slabs with elevated relative humidity levels. Some flooring options, such as a textile composite flooring, perform in areas with elevated moisture. The breathable nature of these flooring products allows moisture to pass through the backing rather than trap it underneath. This method of vapor transmission enables the flooring to be installed with no moisture mitigation as long as the Relative Humidity Test reads 95 percent or below.

Taking these steps prior to installation can save money and mitigate potential flooring system failures.

This article originally appeared in the issue of .

About the Author

David Daughtrey is the director of business development for education with J+J Flooring Group.

Featured

  • California High School Completes Construction on New Makerspace Facility

    Lynbrook High School, part of the Fremont Union High School District (FUHSD) in San Jose, Calif., recently held a ribbon-cutting ceremony for a new Makerspace Building, according to a news release. The district partnered with Quattrocchi Kwok Architects (QKA) for the building’s design and Blach Construction for building services.

  • Missouri K–12 District Cuts Ribbons on Two New Middle Schools

    Springfield Public Schools in Springfield, Mo., recently celebrated the completion of two new middle school facilities with ribbon-cutting ceremonies, according to a district news release. The district officially opened the new Pipkin Middle School and Reed Academy on Sept. 3, both of which were funded through the $220-million Proposition S bond program approved by voters in 2023.

  • Charles R. Drew University Opens Health Professions Education Building

    Charles R. Drew University of Medicine and Science (CDU) has officially opened its new Health Professions Education Building (HPEB) in South Los Angeles.