Construction of Interim Science Building Completed at Saint Louis University

St. Louis Science BuildingMcCarthy Building Companies, Inc. has completed the conversion of a former charter elementary school into an interim science building for Saint Louis University (SLU). The 50,000-sq.-ft. renovation, which was undertaken and opened in time for fall 2017 semester, now houses research, teaching and office space for the University’s Department of Biology. Located on SLU’s South Campus, the new facilities will serve students, researchers and faculty while the University renovates Macelwane Hall, which experienced a fire and subsequent water damage in May 2017.

McCarthy completed the fast-track construction project in seven weeks to ensure the building would be ready for the start of classes on August 28.

“We quickly mobilized our team and collaborated closely with SLU’s staff and Fox Architects to convert the vacant school into a state-of-the-art science learning environment,” says Ryan Freeman, vice president at McCarthy Building Companies. “The project involved a lot of hands-on ingenuity and innovation to meet the very quick timeframe.”

To avoid project delays and reduce costs, the construction team proactively surveyed and sourced laboratory casework and equipment salvaged from the fire, then reworked it to fit the programs and layout in the new spaces. 

Located at the corner of Spring and Chouteau Avenues, the former Imagine charter elementary school building required installation of lab exhaust and other systems and equipment, as well as extensive rework of mechanical and electrical systems to accommodate advanced research and teaching labs. 

“We relied on McCarthy’s efficiency and specialized expertise in building complex research and education spaces to complete the project on time,” says Dustin Montgomery, assistant director of construction services of Saint Louis University.

Featured

  • University of Kansas Opens $400M Football Stadium Reconstruction

    The University of Kansas in Lawrence, Kan., recently announced that the $400-million reconstruction of David Booth Kansas Memorial Stadium is complete in time for the 2025 football season, according to a news release. The university partnered with Turner Construction Company on the project.

  • Different Starting Points, Same End Goal

    Higher education campuses can enhance student experience by implementing mobile credentials to streamline building access, on-campus payments, and access to other amenities. This enables students to connect to their campuses through the technology they use most: their mobile devices.

  • Beyond Four Walls

    Operable glass walls provide a dynamic solution for educational spaces. They align with today’s evolving teaching methods and adapt to the needs of modern learners. Beyond the functional versatility, movable glass walls offer clean, contemporary aesthetics, slim and unobtrusive profiles, and versatile configurations that cater to the evolving needs of students and educators alike.

  • Upcoming University of Alabama Performing Arts Center Hits Construction Milestone

    The University of Alabama in Tuscaloosa, Ala., recently celebrated the topping out of its new Smith Family Center for Performing Arts, according to a news release. The university is partnering with HPM for program and project management on the facility, which broke ground in 2023 and is scheduled for completion in November 2026.

Digital Edition