New Trends in School Construction

North Ridgeville New SchoolConventional, two-grade middle schools are slowly becoming a thing of the past, especially in larger school districts. The traditional K-through-6 elementary and 9-through-12 high school leaves a district with an oddly-sized middle school that can create some logistical challenges.

As most districts grow and replace their 40- or 50-year-old buildings, many are moving toward larger intermediate facilities, taking a load off their elementary schools. This inevitably alters the way school buildings are being built. Bigger middle schools with a wider range of student ages – often grades 5 through 8 – mean that the buildings are divided into distinct areas that actually function as independent schools, all under one big roof. Such is the case at the new, 258,000-square-foot, Grades 3-8, North Ridgeville intermediate school near Cleveland, Ohio.

“This building acts as four facilities within one building envelope,” says Richard Dopatka, Project Manager for ICON Construction Solutions, LLC, the Construction Manager at Risk for the Project. “They all function independently, are divided by firewalls, and are served by separate mechanical rooms. This approach has security, logistical and teaching advantages that more school districts are utilizing.”

ICON combines the sophisticated management expertise of the Scaparotti Consulting Group, the outstanding craftsmanship and general contracting skills of the C.T. Taylor Company and the management resources of Greenspace Construction Services.

ICON was specifically created to provide Construction Management at Risk project delivery for Ohio public entities, with a specific focus on K-12 facilities like North Ridgeville’s new $54 million school. One of the subcontractors ICON selected for the project is MW Mielke, out of Medina, Ohio, and is performing the HVAC and plumbing portion of the job.

“Our focus on institutional and industrial work definitely helped us with the bid on this project,” says Mike Clark, project manager at MW Mielke. “Mielke is a group of three companies; mechanical, construction rigging, and heavy commercial/industrial service.”

In business since 1983, Mielke works primarily in Ohio, but is licensed in 30 states and the US Virgin Islands. The company also has a separate branch in Tampa, Fla.

Soon to accommodate more than 2000 3rd through 8th graders, the North Ridgeville intermediate school project broke ground in July 2015, with completion set for July of this year. Mielke’s work on the North Ridgeville project began in early 2016 as the building shell came together. A 12-man crew was onsite for the duration of the project, supplemented at times with more manpower as needed. Some of the challenges that came up were expected, while others came as a surprise.

“Coordinating with the other trades on a project this size is always a big consideration,” says Clark. “Late in the design phase, we learned that the amount of above-ceiling space available to us was roughly half of what we expected. That threw us a curveball. We ended up having about two feet of overhead space to work with, but still managed to keep most of the ceiling heights at 10 or ten-and-a-half foot.”

The need to pack power, fire suppression, plumbing, communication lines and ductwork into the limited space required installers and engineers to go back to the drawing board. J.M. Verostko, Inc., an MEP firm out of Youngstown, OH, designed the plumbing and mechanical systems for the new school. Their assistance accommodating design changes throughout the project was critical.

Changing the size and shape of ductwork was necessary to make all the components fit in the tightened overhead space. Fortunately, the design of both the HVAC and plumbing systems proved flexible enough to allow the alteration without major changes in equipment or the allotted time schedule. 

The challenge of fitting the HVAC and plumbing components into a smaller space was aided by the fact that J.M. Versotko and MW Mielke took a compartmentalized approach to equipment installation. Rather than a single, large mechanical space, their approach was to have seven mechanical rooms, all serving different portions of the school. “We’ve really grown to like the numerous mechanical and plumbing system approach, and it’s almost a necessity on a building this size,” says  Clark. “Because of the building’s proportions, the sheer size of equipment, piping, ductwork, etc., would have simply been prohibitive. They systems act independently of one another, just as the respective portions of the building do.” 

The school — and the systems that serve it — was designed as four different areas, each with a specific task. Locker rooms, gymnasiums, classrooms, administrative offices, laboratories, kitchens and cafeterias all have very different loads and ventilation needs. Within the building, these are all arranged in a sensible fashion in regard to both student traffic and mechanical system design.

On the plumbing side, a localized approach to supplying domestic hot water was used. There are four mechanical rooms that feature DHW equipment, which that share a space with larger HVAC components. At each of these locations throughout the building’s floorplan, two Bradford White eFSeries commercial water heaters are installed.

Because of proximity to the locker rooms, the mechanical rooms that serve areas One and Three each have two, 300 MBH water heaters, while the mechanical rooms that serve areas Two and Four are have a pair of 199 MBH tanks. All eight of the units have a 100-gallon capacity.

“The water heaters were the recommendation of John Yurcik at Preferred Sales,” says  Clark. “We typically consult with John during the bid process. He goes through the design and helps us determine the best way to meet or exceed the specification.” The manufacturer’s rep firm, Preferred Sales, is based in Hermitage, Pa, and serves portions of Pennsylvania, Ohio, Kentucky and West Virginia. 

“From past projects where Preferred has been involved, we’ve found that the eF Series water heaters to be easy to install and problem free,” continued Clark. “Joe Arra, Bradford White Specialist at Famous Supply, is also a great resource.”

The commercial water heaters offer thermal efficiencies between 92 and 99 percent, courtesy of a three-pass heat exchanger, along with a better recovery rate than similar BTU/Hr. input models.

To maintain immediate availability of hot water at all fixtures, Mielke plumbers installed dedicated hot water recirculation lines, along with Taco pumps and Symmans mixing valves.

Cooling capacity is provided via two, 300-ton Trane chillers on the roof. Three condensing boilers – two 6,000 MBH and a single, 2,000 MBH unit – are used to supply hot water for the building’s hydronic system.

Rooftop air handlers are used in conjunction with VAV boxes and fan coil units to provide individual room conditioning. The air handlers also feature an ERV wheel for cost-effective ventilation. Trane controls were used for the entire HVAC project.

The bulk of Mielke’s work culminated in May. The mechanical systems will provide efficient operation for years to come, and are installed in a manner that service work will be simple.

ICON was proud to turn the building over to the school district in July, on-time and on-budget, offering district maintenance crews more than a month to acclimate to the new facility and the systems that serve it.

Featured

  • Missouri State University Debuts Construction Education Center

    Missouri State University in Springfield, Mo., recently opened a new 10,000-square-foot addition and renovation to support the School of Construction, Design, and Project Management, according to university news. The Construction Education Success Center, built onto the existing Kemper Hall, provides academic space for the school’s construction managers and cost $9.6 million.

  • How One School Reimagined Learning Spaces—and What Others Can Learn

    When Collegedale Academy, a PreK–8 school outside Chattanooga, Tenn., needed a new elementary building, we faced the choice that many school leaders eventually confront: repair an aging facility or reimagine what learning spaces could be. Our historic elementary school held decades of memories for families, including some who had once walked its halls as children themselves. But years of wear and the need for costly repairs made it clear that investing in the old building would only patch the problems rather than solve them.

  • Extron, CENTEGIX Partner for Comprehensive School Security Solution

    Professional audiovisual solutions provider Extron recently announced a partnership with CENTEGIX, which provides rapid incident response technology, to integrate two of their top products in the name of school safety.

  • North Dakota State University Completes Music School Renovation

    North Dakota State University in Fargo, N.D., recently announced that construction on the Challey School of Music has finished, according to a news release. The university partnered with Foss Architecture & Interiors for design and Kraus-Anderson for construction services, and construction began in July 2024.