Master Plan Performance

Master plans seem to be the talk of the universe. It is unquestionably one of the most difficult times in higher education. Funding is being cut at the state level, deferred maintenance continues to climb, and it is becoming more difficult each year to find quality people with the necessary skill sets to replace people leaving and or retiring. Add the issues of the need for new classrooms, fundamentals such as technology for improved student engagement, flexible seating for accommodating numerous types of teaching layouts… and what about if there are changes in leadership that might derail, modify, or discontinue the master plan entirely? With all the items accumulating, choosing just one that keeps us all up at night can be a challenge. At a minimum, the master plan must be the driving force to help stay the course. If implemented correctly and judiciously it can help with this, as well as driving the necessary change the campus might just need to take on the changing landscape.

The History of Bowling Green State University (BGSU)

Established in 1910 on 1,500 acres approximately 30 miles south of Toledo, OH, BGSU’s main campus serves roughly 18,000+ students, with just over 6,000 students living on campus in residential and Greek housing. The campus comprises a building inventory of 100+ buildings, many built to last for generations. Many of the buildings—particularly the Traditions buildings, which are some of the first buildings established on campus—had not been renovated in decades and much of the infrastructure was original. Our master plan study developed in 2009-10 revealed that it would take an investment of over $500 million to eliminate BGSU’s deferred maintenance backlog and accommodate any future needs for flexible scheduling and active learning classrooms. Other considerations were increasing classroom utilization, creating the correct size classrooms, and avoiding single-use or departmental-managed classrooms.

We have taken a different approach to address many of the nagging issues such as deferred maintenance, student demographics, and predicting the new needs of students.

BGSU started with a set of bedrock principles that included providing cutting-edge facilities for students and faculty while determining the best way to reach the greatest number of students, particularly in their first and second years, when retention is so critical: 1) Prioritize learning/classroom and instructional space but also carefully improve space utilization. 2) Remove and decommission as many spaces as possible, being mindful of budgets and sustainability values in building systems and infrastructure. 3) Optimize flexibility and utilization of space, understanding that more usable space will result as renovations occur. 4) Promote doing more with less while providing unique spaces and designs that stimulate opportunities for interaction and engagement for the students, faculty, staff, and community.

Establish Planning Parameters

As the master plan started to develop we thought it was important to cultivate key planning parameters. These included:

  • Addressing the critical needs of BGSU related to one or more of the STEM areas.
  • Providing upgraded facilities to support one or more signature programs.
  • Achieving our classroom space model objectives by improving utilization and active learning principles with the help of the academic groups.
  • Establishing budgets and fundraising goals by developing toughminded decisions criteria based on financial challenges.

Ultimately, we needed to change the BGSU footprint by downsizing the building inventory based on deferred maintenance costs while updating buildings that we determined to be important to the look of campus related to the footprint and location of the building. In the end we were shrinking the campus’ overall footprint, but in doing so we were increasing the density of the campus core.

Acknowledging that it was going to be impossible to accomplish the full scope of upgrades identified, the master plan targeted six underutilized buildings for demolition. The selections were based primarily on three metrics weighted by their importance to the teaching platform: 1) the number of classrooms in a building, 2) the percentage of the overall classroom inventory, and 3) the facility condition index and campus location. Our planning model decision was to focus on four buildings in the academic core that reached the largest number of students and, in the end, improved retention and promoted increased enrollment.

So, how did we do? Be sure to check for my next article…

This article originally appeared in the College Planning & Management September 2018 issue of Spaces4Learning.

About the Author

Bruce A. Meyer, Ed.D., is assistant vice president of Campus Operations at Bowling Green State University, Bowling Green, OH, appointed in April 2010. His team currently manages 5,000,000 square feet on a campus with over 20,000 students, faculty and staff.

Featured

  • Designing Third Spaces That Do What AI Can't

    In 2026, education is evolving faster than ever. With AI reshaping everything from lesson planning to personalized instruction, schools and universities are turning their attention to what AI can’t replicate: spaces that foster collaboration, community, and creativity.

  • Quattrocchi Kwok Architects Opens New Office in Denver

    Education planning and design firm Quattrocchi Kwok Architects (QKA) recently announced that it has opened a new office in Denver, Colo., the firm’s third overall. QKA is headquartered in Santa Rosa, Calif., and runs an East Bay Area office in Oakland.

  • Virginia Tech Tops Out New College of Engineering Building

    Virginia Tech in Blacksburg, Va., recently celebrated the topping out of Mitchell Hall, which will soon stand as the largest College of Engineering building on campus, according to a news release. The university partnered with Skanska on the 285,500-square-foot facility, which has an expected completion date of winter 2028.

  • Academy of Classical Education Breaks Ground in Louisiana

    Charter Schools USA (CSUSA) recently announced the groundbreaking of a new public charter school in Covington, La., according to a news release. The Academy of Classical Education at Covington will enroll students in grades K–8 and is scheduled for completion in August 2026, just in time for the new school year.