A Solution for Leaky Ductwork

Harvard University

Leaky ductwork connected to a new air handling unit in Girguis Lab at Harvard University was fixed with a new approach to duct sealing.

At Harvard University’s Girguis Lab, engineers had just installed a new 8,500 CFM air handling unit that was meant to supply heat to the lab and an adjacent facility. When the unit was brought online, however, its fan was operating at around 97 percent of capacity with little effect—and that was even before the system was connected to the adjacent facility. It was determined that leaks in the ductwork were reducing static pressure to such a degree that air couldn’t reach its destinations. With ducts hidden under insulation and behind layers of pipes, fixing those leaks seemed an impossible task.

Fortunately, the mechanical contractors on the job had heard about a new approach to duct sealing called Aeroseal that worked from the inside of the air shafts to locate and seal leaks.

In just a matter of days, the problem was fixed. The system’s duct leaks were quickly reduced from more than 5,800 CFM down to 429 CFM—a 98-percent reduction. The AHR fan now operated at only 37 percent of capacity. The system was quieter, and university engineers were relieved.

“I would absolutely call this a project saver,” says John Holliser, senior capital project manager for Harvard. “Our only other option was to tear down walls and demolish the building structure in order to access the leaky ductwork. We were very pleased with the results and I honestly don’t know how we would have solved this issue if the Aeroseal technology wasn’t available.”

aeroseal.com

This article originally appeared in the College Planning & Management July/August 2019 issue of Spaces4Learning.

Featured

  • Hawaii Elementary School Breaks Ground on New Classroom Building

    Kealakehe Elementary School in Kailua, Hawaii, recently began construction on a new, $16-million classroom building for its campus, according to a news release. The 13,000-square-foot building will stand two stories and connect the existing upper and lower campuses.

  • From Approval to Opening: Inside Travis Unified School District’s Fast Tracked Campus Expansion

    The Travis Unified School District (TUSD) in northern California includes several elementary and high schools serving over 5,400 students. In 2024, the TUSD Board approved the addition of sixth grade to the Golden West Middle School campus for the 2025–26 school year, setting in motion an accelerated effort to bring new facilities online in less than a year.

  • Embry-Riddle Completes Construction on Research, Lab Facility

    Embry-Riddle Aeronautical University (ERAU) in Daytona Beach, Fla., recently announced the end of construction on a new research and lab facility on campus. The Center for Aerospace Engineering II (CAT II) will support aerospace research and technology development and broke ground last summer.

  • Deferred Maintenance Issues Growing at Universities, Gordian Reports

    U.S. colleges and universities are falling increasingly behind on facilities maintenance and repair, according to Gordian’s 13th annual State of Facilities in Higher Education report. The deferred capital renewal burden has reached $156 per gross square foot, an 8% increase over the previous year.