Four Portland Schools Get Major Upgrades

As classes begin Aug. 28, Portland Public Schools continues construction and renovations on several schools that will be completed in the coming years.

In 2017, voters approved a nearly $800 million bond measure to improve and rebuild four schools. Here’s a brief overview of the district’s construction plans:

Kellogg Middle School

Kellog Middle School's rebuild will include learning suites that promote greater student collaboration.

The original school has been closed for over a decade and was demolished in 2018 to make way for a new building. The $60 million project is headed by OH Planning + Design, Architecture and is set to open in 2021.

Features include:

  • A cafeteria/commons area which serves as the heart of the school;
  • Learning suites that promote greater collaboration;
  • A performing arts stage that opens up to the gym, offering a flexible space for performances, assemblies and other community events;
  • An outdoor, multi-use field and walking path;
  • A STEAM lab and learning garden; and
  • Digital learning tools found throughout the campus for studies in energy use and sustainability.

Madison High School

Madison High School will feature a state-of-the-art performing arts facility.

While the school is under construction, students will attend Marshall High School. The rebuild will add about 170, 000 square feet and will open in 2021. Opsis Architecture, in collaboration with DAO Architecture, hope to transform the school into a “true 21st century learning environment and vibrant center for its thriving, diverse, multicultural, and multi-ethnic community.”

Plans for the school include:

  • A cafeteria/commons area;
  • Science labs;
  • A state-of-the-art performing arts facility;
  • A child care center, public health clinic and community food pantry to serve as resources for the community;
  • A new gym that seats 1,700; and
  • Specialty Career Technical Education labs and a new maker space.

Lincoln High School

Lincoln High School's new building is set to open in 2022 and the new athletic field facilities will be completed by 2023. Bora Architects are spearheading the project.

Construction for the school is planned in two phases and will begin next summer. The school building is set to open in 2022 and the new athletic field facilities will be completed by 2023. Bora Architects are spearheading the project.

Lincoln HS highlights include:

  • A cafeteria, commons and plaza;
  • Specialized classrooms for fine arts and flexible spaces for display of student work;
  • STEM labs and a maker space;
  • A new 1,700 seat gym and new track and field;
  • A 500-seat auditorium, a black box theater and band and choir classrooms; and
  • Specialized classrooms for Career Technical Education courses.

Benson Polytechnic High School

Construction on Benson will start in 2021 after Madison High School is completed. Students and staff would have to be relocated to Marshall High School while construction is underway. Bassetti Architects will spearhead the proposed modernization of Benson. The project is aimed to be completed by 2024.

About the Author

Yvonne Marquez is senior editor of Spaces4Learning. She can be reached at [email protected].

Featured

  • Harvard Announces Replacement Facility for Native American Program

    Harvard University in Cambridge, Mass., recently announced that construction will begin this spring on a new home for its Native American Program, according to university news. The 6,500-square-foot, all-electric building will stand three stories and serve as the central hub for the Harvard University Native American Program (HUNAP).

  • University of Tennessee at Chattanooga Launches New Emergency Communications System

    The University of Tennessee at Chattanooga (UTC) recently deployed a new emergency notification and incident management system for its campus, according to a news release. The university partnered with 911Cellular to launch Safe@UTC, a smartphone app allowing university officials to communicate and respond during emergency situations.

  • Stanford Completes Construction on Graduate School of Education Facility

    Stanford University in Stanford, Calif., recently announced the end of construction on a new home for its Graduate School of Education, according to a news release. The university partnered with McCarthy Building Companies on the 160,000-square-foot project, which involved two major renovations and one new construction effort.

  • University of Arizona Approves New Residence Hall

    The Arizona Board of Regents recently approved plans for a new residence hall at the University of Arizona in Tucson, Ariz., according to a news release. The new facility is scheduled to open in fall 2028 and have the capacity for more than 1,200 students, enforcing a new university expectation that all first-year students live on campus.