Before Renovations Begin, Iowa Middle School Schedules Asbestos Abatement

The Perry School Board of Perry, Iowa, is still accepting construction bids for its $10 million renovation project of Perry Middle School. Before the renovations can begin, the school is pursuing a month-long asbestos abatement project. School Board President Kyle Baxter attributes the reluctance of contractors to submit bids to the renovation project’s tight turnaround time once that abatement is finished.

The asbestos-related work is slated to begin on May 1. In February, the school board’s request to conduct Perry Middle School’s classes remotely for the month of May was denied. Instead, the middle school and Perry High School principals have worked out a plan to hold in-person classes for middle school students at the high school. The whole sixth grade class will set up shop in the PHS multipurpose room. Seventh and eighth grade students will be placed in various empty classrooms throughout the school.

“The reason that we need that month, that four weeks, is that they are saying that abatement is supposed to take four weeks, which would push the project well into September,” said PCSD Superintendent Clark Wicks. “I think it’s better to put that delay—or whatever you want to call it, that virtual piece—in May and start the school year clean. So that is still our goal.”

The students’ last day in the middle school is set for April 23. Movers will come through and clear out the building—removing furniture, projectors, hot spots, and so on—so that the asbestos abatement can begin on May 1.

Perry Middle School Principal Shaun Kruger thanked the PHS principal, as well as his own school’s faculty and students, for their flexibility during the abatement and subsequent renovations. “I’m proud of them,” Kruger said. “They’ve embraced it. They’ve got some multidisciplinary units with the whole group and some other neat ideas planned, and are taking advantage of the opportunity.”

Renovations are scheduled to be completed by the beginning of next school year. “I know there’s some [general contractors] who are interested and asking questions,” said Baxter. “We lost a month of instruction, so part of what we had to do was extend into the fall, so we may be creative in what we have to do over there. Hopefully, we can still get started here in spring break with asbestos and get that rolling.”

Planned renovations for the middle school include expanded and relocated classrooms; updated furniture like student desks, chairs, and classroom fixtures; a new computer lab and STEM lab; new wiring and electrical equipment; updated projectors; and new lighting and ceilings throughout the entire building.

About the Author

Matt Jones is senior editor of Spaces4Learning. He can be reached at [email protected].

Featured

  • Chartwells Launches Campus Dining Evaluation Framework

    Contract food-service management provider Chartwells Higher Education recently announced the launch of BLUEPRINT, according to a news release. The evaluation framework was designed to provide a data-driven and customizable roadmap towards optimizing campus dining services and, by extension, the student experience.

  • school building with glowing circuit board patterns

    AI Is Coming to Schools — But Most School Buildings Still Run on Institutional Memory

    As school districts race to introduce AI into classrooms, administration, and curriculum planning, another conversation is happening behind the scenes: How prepared are school facilities themselves for the operational demands AI will create?

  • Rethinking K-12 Schools as a Continuous Learning Experience

    Most students move through three or more separate facilities during their K-12 journey, yet the built environments they encounter at each stage have traditionally been designed in isolation, with little continuity in spatial language, learning philosophy, or physical resources. Each new school is a reset with different layouts, learning models, expectations, and ways of moving through a building. The next generation of school design is making the case that the first day of kindergarten and the last day of high school can and should feel connected through common support systems and infrastructure in the physical environment.

  • Minnesota District Converts Middle School into Community Hub

    White Bear Lake Area Schools in White Bear Lake, Minn., recently announced the end of a major renovation project that converted a former middle school into a new centralized district and community hub, according to a news release.