Iowa School District Moves Forward on Long-Awaited Bus Barn

In the Spirit Lake Community School District in Spirit Lake, Iowa, the school board has awarded a construction bid for a project that Superintendent Dr. David Smith says has been in the pipeline for quite some time—a “bus barn” to house the district’s school buses. Following the completion of other district improvements like the addition of an Early Childhood Center and renovations to the middle school, Smith said there were enough funds left over to pursue its construction.

Dean Madigan of Madigan Construction was awarded the bid. “It will cost us close to $725,000 in the end with all our expenses, roughly around there, so we’re just really excited to get moving on it,” said Smith.

School bus

Smith said construction will begin soon and that the project is scheduled to be completed by Sept. 1. The bus facility’s new home lies south of the district middle school.

“We’re looking at one full, heated, completely insulated shop,” he said, “and then we’re looking at two other buildings—kind of more of a cold-storage concept to those two, where we will just have a shell of a building…As we move forward, we’ll add insulation. We’ll do other things to make it complete.”

Smith touted the district bus fleet’s perfect inspection record. He said that having a central, heated location for storage and maintenance will serve as a good starting point for future endeavors, as well as provide safety and security benefits.

About the Author

Matt Jones is senior editor of Spaces4Learning. He can be reached at [email protected].

Featured

  • KWK Architects Announces Full Transition to Lawrence Group Branding

    KWK Architects recently announced that it will complete its transition to the Lawrence Group brand effective July 1, according to a news release. The merger marks the end of a three-year strategic integration process that began in March 2023 to unite the firms.

  • Phoenix School District Breaks Ground on New Prep Academy

    The Creighton Elementary School District near Phoenix, Ariz., recently broke ground on a campus replacement for Biltmore Preparatory Academy, according to a news release. The new space will allow the school to expand its enrollment by 50 percent for K–8 students and accommodate modern, collaborative learning styles.

  • Florida District Completes Construction on New Leadership Institute

    Pinellas County Schools near Tampa, Fla., recently announced that construction is complete on the new Dr. Michael A. Grego Leadership Institute, according to a news release. The district partnered with Rowe Architects for the project’s design and with Skanska for construction services.

  • Colorado School District Breaks Ground on Unified PK–12 Campus

    The Haxtun School District No. Re-2J in Haxtun, Colo., recently announced that ground has been broken on a renovation/addition project that will unite its two schools, Haxtun Elementary and Haxtun Jr/Sr High School, according to a news release.