Polished Floors, Right on Schedule

Students and faculty at the Southridge Elementary School in Casper, Wyoming were a bit shocked when they were informed that their brand new school would not be ready for the August 19 start of the school year. Many construction delays were encountered during the project, including the polished concrete floors in the school that were deemed unacceptable by the architect.

The building was 100-percent complete when the decision was made to completely repolish the entire school. Cove base was in place, walls were painted, carpet was laid and cabinets were set. The building was virtually ready to be occupied when the decision was made. A well-known concrete consulting company was hired to assess the situation. Their 20-page report indicated that the floor did not meet the standards of the specification and should be repolished and dyed to the architect’s specification.

Freddie Gwynn, owner of Polished Concrete of Wyoming sat down with the contracting superintendent of the project and discussed the potential remedy. “It’s not going to be cheap, but it will be right” Freddie told him. A rigid timetable to complete the work was laid out. In order to pull this off, Freddie brought in another highly qualified FGS Permashine Contractor, Shawn Weaver of Concrete Floor Systems based in Denver, Colorado.

Plastic was put into place floor to ceiling in order to minimize dust contamination and damaging the finished painted walls. The edging was perhaps the biggest task to tackle. Crews spent countless hours hand grinding and polishing right up to in place carpeting.

Care was taken to densify to complete rejection to ensure that the dye was properly locked in. Final polishing and further densification brought the entire building up to the specified 1500-grit level. What does the school think? “We are very pleased with our floors and with the two contractors,” exclaims Principal Rick Skatula.

This article originally appeared in the issue of .

Featured

  • Deferred Maintenance Issues Growing at Universities, Gordian Reports

    U.S. colleges and universities are falling increasingly behind on facilities maintenance and repair, according to Gordian’s 13th annual State of Facilities in Higher Education report. The deferred capital renewal burden has reached $156 per gross square foot, an 8% increase over the previous year.

  • Big Horn Academy

    Big Horn Academy

    Established in 1999, the Education Design Showcase is a vehicle for showing off innovative — yet practical — solutions in planning, design, architecture, and construction. Big Horn Academy has been recognized with an EDS 2026 Project of Distinction award in the category of New Construction.

  • KWK Architects Announces Full Transition to Lawrence Group Branding

    KWK Architects recently announced that it will complete its transition to the Lawrence Group brand effective July 1, according to a news release. The merger marks the end of a three-year strategic integration process that began in March 2023 to unite the firms.

  • USC Launches Major AI Initiative After $200M Gift

    The University of Southern California in Los Angeles, Calif., recently announced that it has launched a “transformational” new AI initiative thanks to a $200M gift, according to a news release. The project will leverage AI toward breakthroughs and innovations in subjects like the health sciences, business, security, and the arts.