Managing Delays From the Construction Side

Not all construction delays are the fault of the construction contractor. By keeping the lines of communications open, the client and contractor together can work to avoid any serious slowdowns in the project.

Project managers should be aware of early warning of delays caused by the client, main contractor or your own people. Client delays arise because they may change their minds, give instructions too late or are slow in approving drawings and plans. They tend to overlook the fact that these delays push back the start for contractors or sub-contractors, and that the contractor is powerless to avoid these delays.

Main contractor delays usually involve construction work being completed late, causing subsequent stages to fall behind schedule. In some cases, delays are the result of mismanagement and a lack of coordination.

Last but not least, the subcontractors themselves may cause delays; for example, by under-resourcing the project in the early stages or by not completing design drawings and getting them approved on time.

Make sure delays outside your control are recognized and documented. Such delays can impact you financially and need to be recorded and the financial impact dealt with by the responsible party. You should not have to bear the cost of other peoples’ delays, nor should you be blamed for them.

This article originally appeared in the issue of .

Featured

  • Florida District Completes Construction on New Leadership Institute

    Pinellas County Schools near Tampa, Fla., recently announced that construction is complete on the new Dr. Michael A. Grego Leadership Institute, according to a news release. The district partnered with Rowe Architects for the project’s design and with Skanska for construction services.

  • Stanford Online Reveals New Immersive Learning Studio

    Stanford Online recently marked its 30th anniversary with the announcement of a new immersive learning studio, according to a university news release. The studio takes advantage of AI-powered and immersive learning technologies to continue delivering personalized and faculty-led education.

  • Girl Sitting at Library Desk, Using Laptop

    How Campus Design Shapes the Finals Week Experience

    Academic performance is not just about preparation. It is closely tied to how students manage stress, maintain their energy, and shift between work and recovery modes. Much of that is influenced, directly or indirectly, by design.

  • Quattrocchi Kwok Architects Opens New Office in Denver

    Education planning and design firm Quattrocchi Kwok Architects (QKA) recently announced that it has opened a new office in Denver, Colo., the firm’s third overall. QKA is headquartered in Santa Rosa, Calif., and runs an East Bay Area office in Oakland.