Joseph Kushner Hebrew Academy

Project Snapshot

PROJECT: Joseph Kushner Hebrew Academy
LOCATION: Livingston, N.J.
COMPANY NAME: Duro-Last, Inc.
WEBSITE: www.duro-last.com

Joseph Kushner Hebrew Academy

When it became time to replace the roof on the 200,000 square foot Joseph Kushner Hebrew Academy in Livingston, N.J., the school board turned to Duro-Last to get the job done quickly, while school was in session, with minimal interruptions, noise and noxious fumes.

THE CHALLENGE

The EPDM roof was failing and nearing the end of its useful life on the Joseph Kushner Hebrew Academy in Livingston, N.J. Multiple companies offered various solutions for reroofing the 200,000-square-foot facility.

Because the reroofing job was to be done over the existing EPDM system while school was in session, several factors had to be considered prior to choosing a bid. Primarily concerned about the occupants of the building, the Academy’s decision makers wanted a roofing option that would not produce noise or fumes, and would be completed within budget and in a reasonable timeframe.

THE SOLUTION

Although other options were considered, Duro-Last and roofing contractor Complete Roof Systems of Dumont, N.J., were ultimately chosen for several reasons. Not only did Duro-Last’s clean and safe application method meet the requirements necessary for maintaining classes during installation, but it also offered custom prefabrication, mechanical attachment, competitive pricing and an extensive 15-year warranty. The membrane’s high-reflectivity was especially attractive to the board members, as it would save the school energy and money.

Joseph Kushner Hebrew Academy

No small project, the job required flashing approximately 400 penetrations, including 126 HVAC units, on five different roof levels. The flashings used on these penetrations are prefabricated in a Duro-Last plant, prior to delivery to the job site. This Duro-Last prefabrication approach greatly reduces the risk of roof failure caused by human installation errors.

Prefabrication also helps provide the assurance of a roof that’s leak-proof and virtually maintenance-free, and enables Duro-Last to issue its industry-leading warranty.

Because so much of the roof can be manufactured in a controlled factory environment prior to on-site installation, authorized Duro-Last contractors such as Complete Roof Systems can typically complete jobs more quickly and efficiently and with less disruption than contractors using other systems. The school board was impressed by Complete Roof Systems’ ability to finish the job in just 60 days — less than the estimated timeframe — despite consistently poor weather conditions, which hindered the team’s progress.”

Joseph Kushner Hebrew Academy

IMPACT ON LEARNING

Following the wishes of the school board, the installation team was successful in reroofing the Joseph Kushner Hebrew Academy with no interruptions to classes; staff and students inside the building during construction were pleasantly surprised at how quiet the installation was.

Schools across America trust the Duro-Last roofing system because it can provide a quick, interruption-free installation, long-term value and is durable and serviceable.

Editor’s Review

A failing roof presents a health threat to the staff and students, mainly due to moisture issues which have been identified to be associated with respiratory problems. The U.S. EPA’s 2010 study entitled, “How does Indoor Air Quality Impact Student Health and Academic Performance?”, says that substandard environmental conditions in schools can cause serious health problems for children. In addition, it states that IAQ also directly impacts student academic performance. The timing of the fix could create major distractions — noise and fumes. You need to be able to concentrate to learn. That is hard to do if there is a lot of noise or other disrupting activities that are inherent to construction projects. The various players in this project — the school administrators, Duro-Last’s representatives and the roofing company — worked together to keep disruptions to a minimum and to make this process as smooth as possible.

This article originally appeared in the issue of .

Featured

  • California School District Completes Elementary School Modernization

    The San Diego Unified School District in San Diego, Calif., recently held a ribbon-cutting for a whole-site modernization of Pacific Beach Elementary School, according to local news. The school first opened with one building in 1930 and added six more between 1938 and 1957.

  • New Arizona Fine Arts School Reaches Construction Milestone

    Construction of the new Hilltop School for the Arts and Theater in Litchfield Park, Ariz., recently hit a significant milestone, according to a news release. The Agua Fria High School District held a beam-signing ceremony to celebrate the building’s topping out, or the placement of its last structural beam.

  • Photo courtesy of Kraus-Anderson

    Minnesota District Completes $49.7M Addition, Renovation Project

    St. Paul Public Schools in St. Paul, Minn., recently announced the completion of a $49.7-million addition and remodeling project at two district schools, according to a news release.

  • USC Launches Major AI Initiative After $200M Gift

    The University of Southern California in Los Angeles, Calif., recently announced that it has launched a “transformational” new AI initiative thanks to a $200M gift, according to a news release. The project will leverage AI toward breakthroughs and innovations in subjects like the health sciences, business, security, and the arts.