A Solution for Leaky Ductwork

Harvard University

Leaky ductwork connected to a new air handling unit in Girguis Lab at Harvard University was fixed with a new approach to duct sealing.

At Harvard University’s Girguis Lab, engineers had just installed a new 8,500 CFM air handling unit that was meant to supply heat to the lab and an adjacent facility. When the unit was brought online, however, its fan was operating at around 97 percent of capacity with little effect—and that was even before the system was connected to the adjacent facility. It was determined that leaks in the ductwork were reducing static pressure to such a degree that air couldn’t reach its destinations. With ducts hidden under insulation and behind layers of pipes, fixing those leaks seemed an impossible task.

Fortunately, the mechanical contractors on the job had heard about a new approach to duct sealing called Aeroseal that worked from the inside of the air shafts to locate and seal leaks.

In just a matter of days, the problem was fixed. The system’s duct leaks were quickly reduced from more than 5,800 CFM down to 429 CFM—a 98-percent reduction. The AHR fan now operated at only 37 percent of capacity. The system was quieter, and university engineers were relieved.

“I would absolutely call this a project saver,” says John Holliser, senior capital project manager for Harvard. “Our only other option was to tear down walls and demolish the building structure in order to access the leaky ductwork. We were very pleased with the results and I honestly don’t know how we would have solved this issue if the Aeroseal technology wasn’t available.”

aeroseal.com

This article originally appeared in the College Planning & Management July/August 2019 issue of Spaces4Learning.

Featured

  • Arlington High School

    Arlington High School

    Established in 1999, the Education Design Showcase is a vehicle for showing off innovative — yet practical — solutions in planning, design, architecture, and construction. Arlington High School has been recognized with an EDS 2026 Grand Prize award in the category of New Construction.

  • Campus Safety Requires Using Every Resource Available

    Across the U.S., school and campus leaders are facing a security landscape that has changed dramatically over the past decade. Incidents on school property have increased in recent years, with several consecutive years setting record totals. According to analysis of data by CNN, dozens of shootings now occur on school grounds annually across K-12 and higher education environments.

  • California Middle School Breaks Ground on Major Renovation Project

    The Hillsborough City School District (HCSD) in Hillsborough, Calif., recently began construction on new multipurpose and administration facilities for Crocker Middle School, according to a news release.

  • Spaces4Learning Launches 2026 Facilities and Construction Brief Survey

    Spaces4Learning recently launched the 2026 Facilities and Construction Brief Survey, which collects data on the previous year’s K–12 and higher education construction projects nationwide.