A Solution for Leaky Ductwork

Harvard University

Leaky ductwork connected to a new air handling unit in Girguis Lab at Harvard University was fixed with a new approach to duct sealing.

At Harvard University’s Girguis Lab, engineers had just installed a new 8,500 CFM air handling unit that was meant to supply heat to the lab and an adjacent facility. When the unit was brought online, however, its fan was operating at around 97 percent of capacity with little effect—and that was even before the system was connected to the adjacent facility. It was determined that leaks in the ductwork were reducing static pressure to such a degree that air couldn’t reach its destinations. With ducts hidden under insulation and behind layers of pipes, fixing those leaks seemed an impossible task.

Fortunately, the mechanical contractors on the job had heard about a new approach to duct sealing called Aeroseal that worked from the inside of the air shafts to locate and seal leaks.

In just a matter of days, the problem was fixed. The system’s duct leaks were quickly reduced from more than 5,800 CFM down to 429 CFM—a 98-percent reduction. The AHR fan now operated at only 37 percent of capacity. The system was quieter, and university engineers were relieved.

“I would absolutely call this a project saver,” says John Holliser, senior capital project manager for Harvard. “Our only other option was to tear down walls and demolish the building structure in order to access the leaky ductwork. We were very pleased with the results and I honestly don’t know how we would have solved this issue if the Aeroseal technology wasn’t available.”

aeroseal.com

This article originally appeared in the College Planning & Management July/August 2019 issue of Spaces4Learning.

Featured

  • Spaces4Learning Launches 2025 New Product Awards

    Spaces4Learning is now accepting entries for the 2025 New Product Awards! The program’s goal is to honor the outstanding product development achievements of manufacturers and suppliers whose products and services are particularly noteworthy in helping to improve K–12 and Higher Education learning environments.

  • University of Kentucky Integrates New Cleaning Technology

    The University of Kentucky in Lexington, Ky., recently installed a new cleaning system designed to improve cooling efficiency on campus, according to a news release. The Facilities Management’s Utilities and Energy Management Unit installed new chiller tubes into two of the chillers at the university’s Central Utility Plant.

  • Image courtesy of MiEN Company

    6 Ways to Pull Off a Major District Construction Project

    Designing and building a large-scale project on a K–12 campus is a monumental undertaking that requires the right blend of ideas, funding, design and execution to get it right. The process also relies on multiple partners, each of which has to handle its respective aspect of the project while also keeping the district’s broader mission and goals in mind.

  • Gretna East High School

    Gretna East High School

    Established in 1999, the Education Design Showcase is a vehicle for showing off innovative — yet practical — solutions in planning, design, architecture, and construction. Gretna East High School has been recognized with an EDS 2025 Project of Distinction award in the category of New Construction.

Digital Edition