High-School Construction to Finish Early, Under Budget Due to COVID

Construction work on Hendersonville High School, located in Hendersonville, N.C., is set for completion in August 2022—11 months ahead of schedule. The project will also come in about half a million dollars under its $59.1-million budget.

Henderson County Capital Projects Manager David Berry attributes the accelerated timeline to sitework during the summer before construction, as well as a reduced student presence in the school due to the COVID-19 pandemic that allowed workers more and longer access to the site. He announced the news to the Board of Commissioners, who voted to amend its contract with Vannoy Construction to incorporate the new schedule and financial information.

“This is, for me, exciting news to bring forward to this board,” said Berry. “This whole project has been not only the most expensive that Henderson County—I believe—has taken on; it’s been the most difficult. And without everybody’s cooperation, we wouldn’t be where we are.”

The project includes renovations to two campus buildings (the Stillwell Building and the gymnasium completed in 1974) as well as a new-two story building. The new building will play home to administrative offices; a student media center; a new cafeteria; and new science, chorus, and band classrooms. The new building is set to open in August 2021 instead of its original December 2021 completion date.

“Students are going to benefit from this,” said Henderson County Public Schools Superintendent John Bryant. “Taxpayers are going to benefit from this. While logistical challenges will be presented, we welcome those challenges. We know that we’ll be successful in meeting those challenges because they benefit the children of our community.”

About the Author

Matt Jones is senior editor of Spaces4Learning. He can be reached at [email protected].

Featured

  • Schools In Focus: Talking Campus Security with Mitch McKinley

    Furnishing the Future: Adaptive Solutions for Modern Learning Spaces

    On this episode of Schools in Focus, we'll talk about the role that classroom furniture plays in creating adaptive, flexible learning spaces. Our guest is Wesley Edmonds, the Director of Workplace, Adaptive Solutions at OFS.

  • Pangram Secures Funding for AI Detection Technology

    Pangram, which provides technology that detects AI-generated text, recently announced that it has secured nearly $4 million in pre-seed and seed funding, according to a news release. The most recent round of investments, totaling $2.7 million, come on top of the pre-existing seed fund of $1.25 million.

  • Key Considerations for Office-to-Higher-Education Facility Conversions

    Since the onset of the COVID-19 pandemic, office-to-alternative-use conversions have become a recurring subject of urban development discourse. Office utilization rates across major U.S. cities remain below 50%, with vacancy rates exceeding 27% in San Francisco and 16% in New York. Higher education facilities present programmatic and spatial use cases that align readily with the typical characteristics of commercial office buildings.

  • Design Firm Populous Acquires Fentress Architects

    Design firm Populous, which specializes in sports and entertainment venues, recently announced its acquisition of Fentress Architects, based in Denver, Colo., according to a news release. Fentress’ primary focus is aviation projects and public buildings like museums, convention centers, and government facilities

Digital Edition