High-School Construction to Finish Early, Under Budget Due to COVID

Construction work on Hendersonville High School, located in Hendersonville, N.C., is set for completion in August 2022—11 months ahead of schedule. The project will also come in about half a million dollars under its $59.1-million budget.

Henderson County Capital Projects Manager David Berry attributes the accelerated timeline to sitework during the summer before construction, as well as a reduced student presence in the school due to the COVID-19 pandemic that allowed workers more and longer access to the site. He announced the news to the Board of Commissioners, who voted to amend its contract with Vannoy Construction to incorporate the new schedule and financial information.

“This is, for me, exciting news to bring forward to this board,” said Berry. “This whole project has been not only the most expensive that Henderson County—I believe—has taken on; it’s been the most difficult. And without everybody’s cooperation, we wouldn’t be where we are.”

The project includes renovations to two campus buildings (the Stillwell Building and the gymnasium completed in 1974) as well as a new-two story building. The new building will play home to administrative offices; a student media center; a new cafeteria; and new science, chorus, and band classrooms. The new building is set to open in August 2021 instead of its original December 2021 completion date.

“Students are going to benefit from this,” said Henderson County Public Schools Superintendent John Bryant. “Taxpayers are going to benefit from this. While logistical challenges will be presented, we welcome those challenges. We know that we’ll be successful in meeting those challenges because they benefit the children of our community.”

About the Author

Matt Jones is senior editor of Spaces4Learning. He can be reached at [email protected].

Featured

  • Enjoy Tax and Energy Savings with the Right Ceiling Solutions

    Thanks to recent innovations pairing mineral fiber ceiling panels with phase change material technology (PCM), architects, designers, facility managers, and other key players in construction and renovation projects are re-thinking the role ceilings play in supporting environmental objectives—especially energy savings.

  • PNSI Global Alliance Launches New Quality Assurance Certification

    PNSI Global Alliance, a network of technology integrators and service providers, recently introduced a new Quality Assurance Certification (QAC) for AV service and support, according to a press release. The two-day, interactive workshop QAC course is designed for Certified Solution Providers (CSPs) to provide them with the most up-to-date and advanced quality assurance knowledge available.

  • Active Learning Classroom

    Striking a Balance: The Keys to Renovating Science Education Buildings for the 21st Century

    The recent renovation of the Durham Science Center at the University of Nebraska-Omaha (UNO) provides a roadmap for facilities managers tasked with balancing budget constraints, modern pedagogical demands, and long-term sustainability.

  • a traditional red brick school building with the right side visibly deteriorated and the left side well-maintained, surrounded by neat landscaping

    Making the Grade: Navigating Funding Uncertainty in K-12 Schools

    School districts across the country must prepare for all possible funding scenarios by analyzing school asset and infrastructure conditions, understanding their funding needs, and developing a proactive maintenance strategy to stretch their funding dollars.

Digital Edition