Construction Delays Force N.D. School to Delay Opening

A new high school under construction in the West Fargo School District in Horace, N.D., will not be able to open in time for the new school year due to construction delays, according to officials. The district cites a number of issues “mostly beyond the contractors’ control” that will cause Horace High to delay its opening beyond Aug. 26, the district’s scheduled first day of classes.

“There were some issues in terms of timing plan review and permitting, so that sort of delayed the initial groundbreaking,” said Mark Lemer, the district’s construction coordinator. “Now that we’re building in earnest, there are a number of product and material backups that have caused delays in the schedule. The supply chain issues are still out there. They have been plaguing us.”

Gast Construction, the project’s lead contractor, has also faced a significant building materials shortage as worldwide supply costs continue to rise and availability remains low.

Lemer did say that even though contractors around the region have had trouble hiring and retaining workers, Gast did not face such workforce issues. “There were a couple of trades that struggled to get on the site with the appropriate manpower, which caused some impact, but it was not the driving force,” said Lemer.

Roughly 300 freshmen and sophomores will attend classes at Heritage Middle School next door until construction is complete. Lemer also said that while the logistics of schedules and classroom space have already been figured out, the temporary situation is still less than ideal. “The real unfortunate piece is that a middle school really isn’t equipped the same as a high school,” he said. “There will be a few challenges in the coursework we offer, such as construction, chemistry, health careers, advanced bio, and those sort of things that go beyond what we have spaces and equipment for in a middle school.”

The West Fargo school district informed parents of the delayed opening via email. The district said it will continue to send email updates at the beginning of every other week to families at Heritage Middle School and Horace High School to keep them informed.

The district has not yet announced a new opening date for the high school: “What we don’t want to do is get a date out there that we don’t achieve. That would exacerbate the problem,” said Lemer. “We’re looking at a delay that will be beyond the first weeks of school.”

The building was intended to open in phases. The primary building for classes was scheduled to open in August, with music rehearsal spaces, auditoriums and additional classrooms opening later in the year. The project’s later phases have been pushed back even further, and the list of items to be completed in order to open the primary building has been trimmed down. For example, completion of the school’s gym and locker rooms have been added to a later phase.

About the Author

Matt Jones is senior editor of Spaces4Learning. He can be reached at [email protected].

Featured

  • UT-San Antonio Begins Residence Hall Renovations

    The University of Texas at San Antonio recently began a $6-million renovation project to one of its residence halls, according to a news release. Originally completed in 1986, Chisolm Hall measures in at 120,860 square feet and is the oldest and largest residence hall on campus.

  • Q&A: How to Prevent Kitchen Grease Fires in Commercial Kitchens

    School cafeterias and university dining halls serve thousands of meals daily, relying on high-heat equipment like fryers, grills, and ovens. While these operations keep students fed, they also generate significant grease-laden vapors. Without proper controls, this grease becomes a silent fire threat. As a certified exhaust cleaning specialist and business coach who has helped hundreds of institutional facilities achieve NFPA 96 compliance, I emphasize that proactive grease management isn’t optional; it’s a core fire/life safety practice.

  • Nashville Elementary School Receives LEED Gold Certification

    Goodlettsville Elementary School, part of Metro Nashville Public Schools in Nashville, Tenn., recently achieved LEED Gold Certification from the U.S. Green Building Council (USGBC), according to a news release. The 81,750-square-foot school opened in 2023 and was designed by Goodwyn Mills Cawood (GMC).

  • Sam Houston State University Completes Athletic Stadium Renovations

    Sam Houston State University in Huntsville, Texas, recently announced the reopening of Elliott T. Bowers Stadium after an extensive renovation project, according to a news release. The university partnered with Stantec and DLR Group for the project’s design.