Construction Delays First Day of Classes at Nebraska Elementary School

Ada Robinson Elementary School in Lincoln, Neb., had its first day of school on Monday, August 29—two weeks later than planned. The newly built elementary school was originally scheduled to open its doors to students on August 15, but construction delays forced the district to reconsider, according to local news.

On Friday, August 5, just hours after a media tour of the new facility, Superintendent Paul Gausman sent a letter to parents announcing the decision. “Out of an abundance of caution, I do not feel we will be ready to safely open the school building to students on August 15,” he said in the letter. “In order to ensure the safety of all our staff and students, we need to allow the construction team extra time to finish the core areas.”

One wing of the school is still under construction even after the building’s opening, as well as the playground and an open outdoor grassy area, local news reports. These final projects were always intended to continue through the fall, said Lincoln Public Schools.

“We knew when the project started that Robinson always faced a tight and challenging construction timeline amid a global pandemic which caused supply chain challenges and labor shortages,” said Gausman.

The district also announced that, in order to make up the lost time and meet instructional time requirements, the school day will be extended by 17 minutes for the remainder of the school year. Also, it will not offer an early release for the first week of school, unlike all the other schools in the district.

The new facility covers about 85,000 square feet and has capacity for 528 students, according to the district website. About 290 students are projected to attend during the first year. The PreK–5 facility was named after longtime respected district teacher Ada Robinson, who surprised students and staff on the first day of school to welcome them to their new home.

About the Author

Matt Jones is senior editor of Spaces4Learning. He can be reached at [email protected].

Featured

  • California School District Starts Construction on Public Safety Center

    The San Bernardino City Unified School District (SBCUSD) recently announced that construction has begun on a new public safety center that will house the district’s safety and security programs. According to a news release, the James Ramos Center for Public Safety will measure in at 17,140 square feet and contain the district’s Police Department, Office of Emergency Management, and cadet program.

  • modern college building with circuit and brain motifs

    Anthropic Introduces Claude for Education

    Anthropic has launched a version of its Claude AI assistant tailored for higher education institutions. Claude for Education "gives academic institutions secure, reliable AI access for their entire community," the company said, to enable colleges and universities to develop and implement AI-enabled approaches across teaching, learning, and administration.

  • Boosting Student Wellness and Safety Through Indoor-Outdoor School Spaces

    Engaging students through facilities designed for indoor and outdoor learning and activities reflects a growing awareness of how children learn and thrive, with educators recognizing the importance of getting outside and disconnecting from technology. And, as today’s youth grapple with the urgent mental health crisis of increased anxiety and loneliness fueled by both the pandemic and technology, along with a related crisis in youth physical health, the wellness benefits of getting outside have never been so palpable.

  • Clemson to Launch North America’s Largest College Campus Smart Parking Program

    Clemson University in Clemson, S.C., recently announced a partnership with smart parking and curbside management solutions provider eleven-x to launch a smart parking initiative for its population of 29,000 students and faculty, according to a news release.

Digital Edition