Managing Delays From the Construction Side

Not all construction delays are the fault of the construction contractor. By keeping the lines of communications open, the client and contractor together can work to avoid any serious slowdowns in the project.

Project managers should be aware of early warning of delays caused by the client, main contractor or your own people. Client delays arise because they may change their minds, give instructions too late or are slow in approving drawings and plans. They tend to overlook the fact that these delays push back the start for contractors or sub-contractors, and that the contractor is powerless to avoid these delays.

Main contractor delays usually involve construction work being completed late, causing subsequent stages to fall behind schedule. In some cases, delays are the result of mismanagement and a lack of coordination.

Last but not least, the subcontractors themselves may cause delays; for example, by under-resourcing the project in the early stages or by not completing design drawings and getting them approved on time.

Make sure delays outside your control are recognized and documented. Such delays can impact you financially and need to be recorded and the financial impact dealt with by the responsible party. You should not have to bear the cost of other peoples’ delays, nor should you be blamed for them.

This article originally appeared in the issue of .

Featured

  • Round Rock ISD Completes New Early College High School

    Round Rock ISD near Austin, Texas, recently announced that construction is complete on a new, 46,500-square-foot campus for Early College High School, according to a news release. The new facility will allow the school’s students and staff to move from portables into a permanent building and increase its enrollment to 500.

  • College of the Desert Hits Construction Milestone on New Campus

    College of the Desert recently announced that the construction of its new Palm Springs Campus in Palm Springs, Calif., recently reached a major construction milestone, according to a news release. The college is partnering with general contractor C.W. Driver Companies, which recently “topped out” the facility by placing the final beam in its structure.

  • Stanford Completes Construction on Graduate School of Education Facility

    Stanford University in Stanford, Calif., recently announced the end of construction on a new home for its Graduate School of Education, according to a news release. The university partnered with McCarthy Building Companies on the 160,000-square-foot project, which involved two major renovations and one new construction effort.

  • Surging Demand for Student Housing Fuels Major Campus Investment Opportunities

    University leaders throughout the U.S. are accelerating plans to modernize and expand student housing as enrollment stabilizes and demand for on-campus living rebounds. Recent data from the National Center for Education Statistics indicates that total postsecondary enrollment is projected to grow through the end of the decade, with undergraduate enrollment alone expected to increase by more than 8 percent by 2030.