New Jersey Schools Development Authority Announces Success of Program Overhaul

Design-Build Approach Shows Benefits to Budget and Schedule

Trenton, N.J. – At yesterday’s monthly board meeting of the New Jersey Schools Development Authority (NJSDA), NJSDA Board Members were provided with an update regarding the success of new processes and approaches implemented under the Christie Administration. The presentation focused on 12 projects that have been approved as part of the NJSDA’s Capital Project Portfolio. Of the projects studied, all projects were completed within or under budget.  Eleven of the projects were delivered either before or as originally projected including four that were delivered ahead of schedule.

“The positive results shared today were achieved through the significant programmatic and organizational changes instituted at the NJSDA under the Christie Administration,” said NJSDA CEO Charles McKenna. “Our record of routinely completing construction projects within anticipated budget and timelines highlights the success of the State’s school construction program. We are getting it right here in New Jersey.”

Another significant benchmark examined was the total change orders experienced on the projects reviewed. The 12 projects evaluated experienced an average of 2.2 percent in change orders per project. Those built through the design-build approach, the method currently most utilized by the NJSDA, experienced an average of only 0.5 percent in change orders per project. In comparison, prior to the Christie Administration (from 2006 to 2009), construction contracts for 17 projects that received a notice to proceed experienced an average of nearly 12.2 percent in change orders. That equates to a savings of more than $2 million per project on average compared to portfolio projects completed in prior years.

“NJSDA’s use of the design-build approach and an expanded constructability review process has resulted in fewer schedule delays and change orders,” said NJSDA Chairman Edward Walsh. “These significant accomplishments highlight the NJSDA’s proficiency in the management and construction of school facilities projects throughout New Jersey. The Authority is delivering efficiently designed, high-quality educational facilities that best meet the needs of New Jersey’s students while ensuring proper management of taxpayers’ resources.”

Seven of the 12 projects completed utilized the design-build approach, which differs from the traditional method in that NJSDA contracts with one firm for both design and construction of a school facilities project. This approach also allows for some design and construction activities to proceed concurrently through phased advancement, which has been found to improve upon project timelines.

For the remaining five projects advanced through the design-bid-build approach, the NJSDA implemented an enhanced constructability review process. The Constructability Review provides a contractor with an opportunity to analyze the contract documents (plans and specifications) to identify any issues that would impact the schedule or cost of completion, so that such issues can be resolved before commencement of construction. Through this process, NJSDA has experienced a substantial reduction in unforeseen issues, schedule delays and change orders.

The SDA manages the design and construction of school facilities projects in New Jersey’s 31 SDA Districts. The SDA is responsible for financing 100 percent of the cost of school facilities projects in SDA Districts. The SDA also provides grants of at least 40 percent of the eligible costs to New Jersey’s Regular Operating Districts. The SDA’s current portfolio of active projects is valued at $2 billion – including the Capital Project Portfolio, emergent projects, and Regular Operating District grants.

Featured

  • Can AI Help Build Stronger Communities in Student Housing?

    Student housing success is shifting from operational performance to student experience, with belonging now at the center. A recent 2025 report underscores a growing emphasis on student well-being, community, and engagement, signaling that expectations now extend beyond logistics to ensure students feel supported in their living environments. AI is enabling that shift by reducing administrative workload and giving teams more time to focus on meaningful student engagement.

  • Johns Hopkins Starts Construction on New Residence Hall, Dining Facility

    The Homewood Campus of Johns Hopkins University in Baltimore, Md., recently began construction on a new residence hall and dining facility, according to university news. The work involves demolishing the existing Alumni Memorial Residence Hall I, which was built in 1923, to make room for the new facility.

  • UT-San Antonio Begins Residence Hall Renovations

    The University of Texas at San Antonio recently began a $6-million renovation project to one of its residence halls, according to a news release. Originally completed in 1986, Chisolm Hall measures in at 120,860 square feet and is the oldest and largest residence hall on campus.

  • St. John Fisher University

    Classroom Revitalization – Basil Hall Room 216

    Established in 1999, the Education Design Showcase is a vehicle for showing off innovative — yet practical — solutions in planning, design, architecture, and construction. St. John Fisher University's Basil Hall Room 216 Classroom Revitalization has been recognized with an EDS 2026 Project of Distinction award in the category of Spaces.