Concrete Slab Configuration Raises Concerns Among Sports Flooring Installers

OAKBROOK TERRACE, IL – Concrete slab configuration is very important in the success of a new maple floor installation.  Placing a below-slab vapor barrier directly beneath the concrete slab is proper and typical.  Placing any type of fill material between the below-slab vapor barrier and the concrete slab frequently causes moisture-related problems with the finished maple surface.

The Maple Flooring Manufacturers Association (MFMA) requires the general contractor to provide a concrete slab troweled smooth and flat to a tolerance of 1/8 of an inch in a 10-foot radius, subject to the approval of the MFMA wood flooring contractor. By placing sand between the vapor barrier and the slab, a flatter concrete slab with less initial curling can be produced.  However, this configuration allows the sand to act like a sponge—trapping moisture within the sand layer during the concrete pour. Over time, trapped moisture can migrate up through the concrete slab and cause moisture-related difficulties with subfloor components and the finished wood flooring surface.

The only MFMA-recognized method for reading concrete moisture levels within a slab is by testing its relative humidity. Please refer to the instructions of the manufacturer’s relative humidity test kit for complete details on how to administer the test correctly. MFMA recommends the relative humidity level for a concrete slab for a non-glue-down maple floor system be 85 percent or lower and for glue down systems the concrete slab relative humidity level should be 75 percent or lower before installation.For concrete relative humidity conditions above MFMA’s recommendation consult your MFMA Sport Floor Contractor or your MFMA Manufacturer.

For more information regarding variations to MFMA’s recommended concrete slab configuration, please contact MFMA’s technical director at 888/480-9138 or email [email protected].

Featured

  • Universities Continue to Launch Multimillion-Dollar Campus Transformations

    What makes the current wave of campus development especially noteworthy is its emphasis on multi-use functionality and community integration. Institutions are no longer investing solely in academic or athletic facilities in isolation. Instead, they are creating destinations that blend recreation, health, housing, and event-driven economic activity.

  • UTampa Breaks Ground on STEM Academic Facility

    The University of Tampa in Tampa, Fla., recently broke ground on one of its largest academic facilities ever, according to a news release. The Dickey Science Innovation Center will measure 153,000 square feet and has a scheduled completion date of fall 2028.

  • University of Kansas Breaks Ground on Entrepreneurship Hub

    The University of Kansas in Lawrence, Kan., recently held a groundbreaking ceremony for the new KU Entrepreneurship Hub, according to university news. The Hub is part of the university’s School of Business and will include spaces for experiential learning and programming.

  • ed tech conference calendar

    Upcoming Awards, Events & Webinars