A Solution for Leaky Ductwork

Harvard University

Leaky ductwork connected to a new air handling unit in Girguis Lab at Harvard University was fixed with a new approach to duct sealing.

At Harvard University’s Girguis Lab, engineers had just installed a new 8,500 CFM air handling unit that was meant to supply heat to the lab and an adjacent facility. When the unit was brought online, however, its fan was operating at around 97 percent of capacity with little effect—and that was even before the system was connected to the adjacent facility. It was determined that leaks in the ductwork were reducing static pressure to such a degree that air couldn’t reach its destinations. With ducts hidden under insulation and behind layers of pipes, fixing those leaks seemed an impossible task.

Fortunately, the mechanical contractors on the job had heard about a new approach to duct sealing called Aeroseal that worked from the inside of the air shafts to locate and seal leaks.

In just a matter of days, the problem was fixed. The system’s duct leaks were quickly reduced from more than 5,800 CFM down to 429 CFM—a 98-percent reduction. The AHR fan now operated at only 37 percent of capacity. The system was quieter, and university engineers were relieved.

“I would absolutely call this a project saver,” says John Holliser, senior capital project manager for Harvard. “Our only other option was to tear down walls and demolish the building structure in order to access the leaky ductwork. We were very pleased with the results and I honestly don’t know how we would have solved this issue if the Aeroseal technology wasn’t available.”

aeroseal.com

This article originally appeared in the College Planning & Management July/August 2019 issue of Spaces4Learning.

Featured

  • Round Rock ISD Completes New Early College High School

    Round Rock ISD near Austin, Texas, recently announced that construction is complete on a new, 46,500-square-foot campus for Early College High School, according to a news release. The new facility will allow the school’s students and staff to move from portables into a permanent building and increase its enrollment to 500.

  • Houston-Area High School Breaks Ground on 117,000SF Multi-Use Facility

    North Shore Senior High School, part of Galena Park ISD in Houston, Texas, recently broke ground on a new multi-use facility for student extracurriculars, according to a news release. The North Shore Multi-Use Facility will include dedicated practice and training space for the school’s athletics and fine arts programs.

  • Harvard Announces Replacement Facility for Native American Program

    Harvard University in Cambridge, Mass., recently announced that construction will begin this spring on a new home for its Native American Program, according to university news. The 6,500-square-foot, all-electric building will stand three stories and serve as the central hub for the Harvard University Native American Program (HUNAP).

  • California K–12 District Finishes Renovations on Multi-Sport Stadium

    The Alameda Unified School District (AUSD) in Alameda, Calif., recently announced the completion of a renovation project on the Encinal Jr. & Sr. High School stadium, according to a news release. The district partnered with Quattrocchi Kwok Architects (QKA) and Bothman Construction on the facility, and funding came from Bond Measure B.