Laredo ISD Provides Updates on $100M in District Construction Projects

The Board of Trustees for the Laredo Independent School District in Laredo, Texas, recently received updates on a series of district construction projects totaling about $100 million, according to local news. Ongoing projects include a new academic wing for Cigarroa High School, a replacement facility for Cigarroa Middle School, a new library for Heights Elementary School, and construction of the new Kawas Elementary School.

According to Assistant Superintendent for Plant Facilities and Support Services Angel E. Velazquez, the new academic wing at Cigarroa High School will soon finish construction of Phase 1, which will house the campus’ core instruction areas. After the completion of Phase 1, demolition of the former instruction wings will begin to clear space for Phase 2, which entails the campus’ vocational shops, according to local news. The project cost an estimated $21 million and is scheduled for completion in late August 2023.

Meanwhile, the district is also planning a new, ground-up facility for Cigarroa Middle School. “This brand-new campus will replace completely the existing facility and will include instructional classrooms, fine art areas, cafeteria, two gymnasiums, special education units, and all required administration areas,” said Velazquez. The project cost $55 million and will be completed in March 2025.

The library at Heights Elementary School saw renovations to include four additional classrooms necessitated by increased enrollment, said Velazquez. The renovation project cost $3 million and will be completed by next month.

Finally, the district is constructing a new elementary school, Kawas Elementary School. “We are currently in the process of completing the construction of the new Kawas Elementary Campus,” said Velazquez. “The total cost of this brand-new facility is $16.4 million and is expected to be substantially completed by October 2023. The scope of work includes classrooms, gymnasium, cafeteria, and administration areas. The existing early childhood area was kept due to its good condition and will be seamlessly connected to the new building, improving the overall security of the facilities.”

Funding for all four projects comes from a 2018 Bond series election approved by LISD taxpayers, local news reports.

About the Author

Matt Jones is senior editor of Spaces4Learning. He can be reached at mjones@1105media.com.

Featured

  • Aims Community College to Build Workforce Innovation Center

    Aims Community College in Greeley, Colo., recently announced that it has broken ground on its new Aims Workforce Innovation Center (AWIC), according to a news release. The facility for workforce development, entrepreneurship, and education has a scheduled opening date of fall 2026.

  • PNSI Global Alliance Launches New Quality Assurance Certification

    PNSI Global Alliance, a network of technology integrators and service providers, recently introduced a new Quality Assurance Certification (QAC) for AV service and support, according to a press release. The two-day, interactive workshop QAC course is designed for Certified Solution Providers (CSPs) to provide them with the most up-to-date and advanced quality assurance knowledge available.

  • Rice University to Build New Student Life Complex

    Rice University in Houston, Texas, recently announced that a groundbreaking ceremony for the upcoming Moody Center Complex for Student Life (MCCSL) will take place on May 8, 2025, according to a university news release. The 75,000-square-foot facility was designed by architecture firm Olson Kundig with Page serving as executive architect, and it has an estimated completion date of fall 2027.

  • California High School Debuts $35M Performing Arts Center

    Irvine High School in Irvine, Calif., recently opened its new Performing Arts Center built in partnership with C.W. Driver Companies, according to a news release. The facility cost $35 million and covers about 25,000 square feet.