Recalibrate, Retune, Rebalance

When some students in a building are wearing jackets to stay warm and others are wearing shorts to stay cool, it is time for retrocommissioning. Commissioning new construction ensures that building systems are functioning as designed for a planned use; retro- or recommissioning retools older building systems while optimizing design conditions based on actual use. The goals are user comfort, right-sizing flows for actual use, energy efficiency and cost savings.

Catalyst for Growth

In Glassboro, NJ, Rowan University’s new $70.6 million engineering building already was under construction when it became clear that the 1996-built Rowan Hall needed a tune-up. The landmark structure for the Henry M. Rowan College of Engineering, Rowan Hall is occupied by 600 students, faculty and staff, morning to night, every day of the week. Designed by Ballinger nearly 20 years ago, the elegant building on a pond is home to multiple engineering disciplines, including biomedical, chemical, civil and environmental, mechanical, and electrical and computer engineering. It is the 99,349-square-foot tribute to the philanthropist whose generosity created the College of Engineering and served as the catalyst for the growth of the entire university.

Since the building opened, the engineering enrollment at the university has doubled, increasing stress to the building systems every year. At times it was uncomfortable to work there, and end users complained of temperature, humidity and airflow problems. This is not unusual. System controls in every building need to be recalibrated over time. Controls drift out of calibration, wires get snipped, dampers bind, airflow stations become dirty, devices or logic get bypassed, new equipment overloads the system, fume hoods are added, and doubling the number of users can certainly impact how well airflow is transmitted.

Recommissioning

Research and laboratory buildings in particular need to have HVAC systems in good working order and should be recommissioned ongoing with comprehensive calibration every five years. The Rowan recommissioning project began with certified balancing professionals who took readings of the current air flows/water throughout the building to establish a baseline of as-found readings. Labs have a significant amount of ventilation air brought in and contaminated air exhausted out through fume hoods and other devices. Critical to the safety of users, fume hoods are also required to be recertified annually.

Even classrooms and lab spaces without fume hoods may have tight positive or negative pressure requirements, and flow stations and static pressure sensors can malfunction if they become dirty or clogged. Since they are indispensable to the operation of the HVAC systems, annual checking and recalibrating is required. The next phase is to recalculate the building’s loads based on actual use. Buildings are designed for a certain occupancy and program, but both change over time and the building systems don’t always keep up with the modifications. There are more people using Rowan Hall now than when it was constructed, and the machines and equipment have changed.

Once the load study and air change rates have been identified, a professional engineer will redirect the systems to obtain the correct flows, and the facility will be rebalanced and recommissioned. The university may ultimately need to invest in new control sensors or other components, but they are likely to be of better quality today than when the building was built. Overall, the cost savings will far outweigh the cost of new technology.

As part of the project, an independent commissioning firm will evaluate, test and correct the existing HVAC control systems and components to meet current facility requirements, optimize function and energy efficiency and improve comfort. This process involves investigation, analysis and corrective action of the building systems.

Payback

A building like Rowan Hall is very energy-intensive, so the savings may be realized very quickly after recommissioning. As with Rowan Hall, the university’s Science Building had airflow and temperature issues a few years ago. Recommissioning reduced the energy consumption in that building by 40 percent and eliminated the complaints.

Whatever the building program, system equipment and controls are constantly changing, some at a more accelerated pace than others. After two to three years, every building has drifted or changed to the point where a recommissioning effort will result in cost savings and improved comfort and operation.

This article originally appeared in the issue of .

About the Authors

William Wright is the president of Wright Commissioning, based in Philadelphia.

Joe Monahan is the assistant vice president for Planning & Construction at Rowan University.

Featured

  • Springfield Breaks Ground on $53.7M Pipkin Middle School Rebuild

    Construction is underway on a new, state-of-the-art Pipkin Middle School in Springfield, Mo., a major step in Springfield Public Schools’ (SPS) long-term facility improvement plan, according to local news. The $53.7-million project officially broke ground in early June, following years of planning and community input aimed at modernizing aging infrastructure and addressing student capacity concerns.

  • ProTeam Launches GoFit 6 HEPA Backpack Vacuum

    Technology leader Emerson recently introduced the new ProTeam GoFit 6 HEPA backpack vacuum, according to a news release. The vacuum was designed to capture 99.97% of particulates down to 0.3 microns—including atmospheric hazards like lead dust, mold spores, and other particulates—through an advanced filtration system.

  • California High School Starts Construction on New CTE Building

    Analy High School, part of the West Sonoma County Union High School District (WSCUHSD) in Sebastopol, Calif., recently broke ground on a new Career Technical Education (CTE) Building, according to a news release. The 15,000-square-foot facility will offer specialized facilities for students in engineering, welding, culinary arts, agricultural sciences, and design thinking.

  • modern college building with circuit and brain motifs

    Anthropic Introduces Claude for Education

    Anthropic has launched a version of its Claude AI assistant tailored for higher education institutions. Claude for Education "gives academic institutions secure, reliable AI access for their entire community," the company said, to enable colleges and universities to develop and implement AI-enabled approaches across teaching, learning, and administration.

Digital Edition